About estimated costs for a production order

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

The estimate task calculates estimated costs for a production order. The calculations of estimated cost are based on the quantity in the production order, the components in the production bills of materials (production BOMs), the routing operations in the production route, the indirect costs that apply to these components and operations, and the active cost data as of the calculation date. If there is a phantom line item in the production BOMs, the calculations reflect the phantom's components and route operations.

The estimate task can be used to recalculate estimated costs to reflect updated information. For example, the updated information can be changes to the quantity in the production order, the components in the production BOMs, the routing operations in the production route, the indirect costs that apply to these components and operations, or the active cost data as of the recalculation date.

The calculations of estimated cost also suggest a sales price for the production item, based on a cost-plus-markup approach.

The calculations of estimated cost can optionally apply to reference orders that reflect production orders that are linked to the production order.

See also

About analyzing costs for a production order