While reporting task status in Microsoft Project Web App, you may find that you want to report on a task that is not showing up in the list.

  1. On the Quick Launch, in the My Work section, click Tasks.

  2. On the Tasks tab of the ribbon, in the Tasks group, click the arrow under Insert Row.

  3. Choose how you want to add a task:

    • Create a New Task   Create a new task within an existing project, and then add that task to your task status.

    • Add Yourself to a Task   Assign yourself to an existing task, and then add that task to your task status.

    • Insert Team Tasks   Assign yourself to one of your team tasks, and add that task to your task status.

Once you have added a task to your task status, you can enter your progress on that task.

Änderungsverlauf

Datum Beschreibung

27. Januar 2011

Erstveröffentlichung

Fanden Sie dies hilfreich?
(1500 verbleibende Zeichen)
Vielen Dank für Ihr Feedback.
Anzeigen:
© 2014 Microsoft