How to: Create, Delete, or Modify a Shared Schedule (Report Manager)
-
In Report Manager, click Site Settings on the global toolbar.
Note: If Site Settings is not available, you do not have permission to access site settings. -
In the Other section on the page, click Manage shared schedules.
-
To create a new schedule, click New Schedule. To edit an existing schedule, click the name of the schedule.
-
Type a descriptive name for the schedule.
-
Select Hour, Day, Week, or Month. Click Once to create a schedule that runs one time only. Additional options appear when you specify the basis of your schedule.
-
Optionally select a date to start the schedule. The default is the current day. You can postpone the schedule start time by choosing a later date.
-
Optionally, select a date to end the schedule. The schedule stops running on this date, but is not deleted.
-
Click OK.
-
In Report Manager, click Site Settings on the global toolbar.
Note: If Site Settings is not available, you do not have permission to access site settings. -
In the Other section on the page, click Manage shared schedules.
-
Select the check box next to the schedule you want to delete, and then click Delete.
Concepts
Creating, Modifying, and Deleting SchedulesShared Schedules and Report-Specific Schedules