
Production:Warm (Non-Dedicated) with Two Active Directory Sites
In the Production:Warm (Dedicated) configuration, the Edge Transport, Hub Transport, and Client Access servers in the backup datacenter are dedicated as standby resources for Datacenter A. That configuration represents a significant hardware investment that is not being fully used. An alternative model is represented in the following figure.
Example of a Production:Warm (Non-Dedicated) deployment.gif)
Production:Warm (Non-Dedicated) requires the administrator to manually trigger activation of the backup datacenter. When triggered, the activation process reconfigures some equipment and infrastructure in the backup datacenter to take over messaging service for the users of Datacenter A.
As with the Production:Warm (Dedicated) solution, there are two Active Directory sites in the Production:Warm (Non-Dedicated) solution. But unlike the Production:Warm (Dedicated) solution, both Active Directory sites span to the other datacenter. The dedicated resources in the backup datacenter have become redundant servers for a different production configuration in the backup datacenter. This approach makes these resources available for normal use, thereby creating two production datacenters that are effectively a backup for each other.
For example, as shown in the figure Example Production:Warm (Non-Dedicated) deployment, when Datacenter A fails, Hub Transport server 4, Client Access server 4 and Global Catalog server 4 are added to Active Directory site Redmond, and in conjunction with Redmond NodeB, serve the users of Datacenter A to deliver the messaging service. After the site failure, the two production environments are now running at reduced capacity and reduced redundancy compared with their normal state. Assuming their ongoing load can be supported, this configuration is acceptable. For example, Internet mail is going through the Edge Transport server in Datacenter B. To support an extended datacenter outage, the business can have vendor contracts that rapidly provide additional hardware when requested. The added hardware could then be used to restore redundancy or add additional capacity.
The normal operation of the Redmond and Dublin Active Directory site deployments would be the same for this solution as they are for the Production:Warm (Dedicated) solution. Similarly, the network bandwidth between the two locations would have the same driving factors, except that both Redmond and Dublin servers need to be concurrently supported.
Activation of the backup datacenter is done by either:
-
Moving the active node and clustered mailbox server to the operating datacenter’s Active Directory site.
-
Moving Hub Transport, Client Access, and directory servers in the backup datacenter into the failed datacenter’s Active Directory site.
The recommended activation solution is to move the Hub Transport and Client Access servers into the failed datacenter’s Active Directory site. This solution results in the simplest and least disruptive activation.
In this solution, the recovery of Datacenter A is accomplished by these high-level steps:
-
The network infrastructure is brought online. It is possible that no network infrastructure changes are required because Internet mail is already being received by Datacenter B.
-
The Active Directory infrastructure for Datacenter A is brought online (Active Directory site Redmond).
-
The remaining Mailbox server is brought online. This step may involve forcing the cluster to come online with the single remaining server.
-
The Active Directory site Redmond is updated with the IP addresses of Hub Transport server 4, Client Access server 4, and Global Catalog server 4.
-
Client Access server 3 is added to the NLB configuration for Redmond.
-
Datacenter A messaging service is restored.
When Datacenter A is available, Datacenter B can be restored to its normal configuration using these high-level steps:
-
Datacenter A individual servers are brought online. They will participate in providing the service unless Exchange services are manually stopped or disabled. When migrating back, allow Datacenter A servers to come online.
-
Allow Hub Transport server 4 to drain its queues, and then take it offline.
-
Take Client Access server 4 out of the NLB configuration. Clients will still be able to connect to the servers in Datacenter A.
-
Perform any required networking infrastructure updates.
-
Move the clustered mailbox server to Datacenter A.
-
Update Active Directory site Dublin with the IP addresses of the servers that were moved during the activation.
-
Both datacenters are restored to their original condition.
As with any site failure solution, the activation of the production and backup datacenter should be scripted and tested regularly. Using a clustering solution for the Mailbox server decreases activation times for the backup datacenter. Other mailbox solutions may have some DNS and Active Directory replication required that can affect when mail flow resumes and clients are able to access their mailbox.
This solution allows the servers used for site resilience to be applied to normal operation. This may decrease the cost of the site resilience solution, but it risks not being able to sustain complete system load when required. For example, should the load on the Hub Transport servers in Datacenter B grow to use 80 percent of the capacity, activation of the backup Datacenter for A will exceed Hub Transport capacity. With this solution, administrators must be careful in tracking system utilization over time to make sure that the solution remains viable. Should the load increase, you will need to acquire and deploy new hardware.