Deploying a Worldwide Site Consolidation Solution for Exchange Server 2003 at Microsoft
Deploying a Worldwide Site Consolidation Solution for Exchange Server 2003 at Microsoft
Technical White Paper
Published: June 11, 2004 | Updated: August 9, 2004
Using Microsoft Exchange Server 2003 and Microsoft Office Outlook 2003
to consolidate more than 75 messaging sites worldwide into seven physical locations
|
Situation
|
Solution
|
Benefits
|
Products & Technologies
|
|
Microsoft had a distributed Microsoft Exchange Server 2003 infrastructure that spanned
over 70 physical sites worldwide. The messaging infrastructure was complex and expensive
to operate, particularly with the high rate of change within Microsoft IT.
|
Microsoft consolidated user mailboxes from servers located in local offices to a
smaller number of clustered Exchange Server 2003 installations in regional data
centers. To enable this consolidation, Microsoft IT deployed Microsoft Office Professional
Edition 2003, with Exchange Cached Mode enabled for Microsoft Outlook 2003, which
provides higher productivity in remote and offline scenarios.
|
- Reduced number of mailbox servers by nearly 75 percent, sites by over 90 percent
and associated operational costs, resulting in overall messaging cost reduction
of at least four percent, while still using more robust storage system hardware
- Maintained user satisfaction and productivity by reducing dependency on real-time
network connectivity.
- Created additional opportunities for secondary consolidation of additional
servers and tail sites.
|
- Microsoft Windows Server 2003, Enterprise Edition
- Microsoft Active Directory directory service
- Microsoft Exchange Server 2003
- Microsoft Office Professional Edition 2003 (including Microsoft Outlook 2003
deployed with Exchange Cached Mode enabled)
- Microsoft Operations Manager 2000
- Storage Area Networks (SANs)
|
Executive Summary
Prior to deploying its physical site consolidation solution, the Microsoft IT group
used pre-release versions of Microsoft® Exchange Server 2003 and Microsoft Office System 2003
to upgrade its existing Exchange Server 2000 messaging platform. Microsoft
IT then undertook the deployment of its physical site consolidation solution to
reduce the number of physical locations running Exchange Server from 75 to
seven physical sites (six regional data centers [RDCs] plus one Exchange site in
Johannesburg, South Africa).
The Exchange Messaging team worked in conjunction with several teams from across
Microsoft to redesign and deploy the Exchange Server 2003 site consolidation
solution. This solution not only reduced the number of physical sites, Exchange
servers, and other supporting servers, but also continued to deliver high employee
satisfaction and productivity measurements and create opportunities for further
server consolidation.
The Exchange Server 2003 physical site consolidation is a key component
of the internal Model Enterprise (ME) initiative at Microsoft. The goal of the ME
initiative is to model a continuously optimized enterprise infrastructure that satisfies
the business needs of Microsoft by striking the right balance of availability, performance,
flexibility, and cost – while using Microsoft products and solutions wherever
possible. A key component of the ME initiative is the optimization of the overall
enterprise total cost of ownership (TCO) for the Microsoft IT infrastructure taking
into account Microsoft IT's unique role testing and deploying new versions of Microsoft
software in a production enterprise environment.
The specific objectives of the Exchange Server 2003 physical site consolidation
were to:
- Reduce the number of worldwide physical sites running Exchange Server 2003
servers from the current number of 75 to six RDCs (plus one remaining tail site)
aligned with the Microsoft ME Initiative.
- Detailed analysis of the attendant reduction in annualized costs associated with
the reduction in the number of Exchange Server physical sites.
- Accurately monitor, gather, analyze, and report on changes in network bandwidth
utilization and latency directly related to the Exchange Server physical site
consolidation.
- Measure any perceived changes in Microsoft employees' Microsoft Office Outlook®
client user experience through surveys taken before and after the physical site
consolidation.
- Document Microsoft IT's Exchange Server physical site consolidation experiences,
best practices, and new lessons learned for the benefit of Microsoft customers.
To address these objectives, Microsoft IT moved toward a fully clustered mailbox
server environment running on a smaller number of regionally located data centers.
Each of these server clusters is connected to one or more Storage Area Network (SAN)
enclosures for its data storage. The use of clustering technology has improved reliability
and increased availability.
The planning, design, and deployment of the Exchange Server 2003-based
physical site consolidation solution by the Microsoft IT Exchange Messaging team
met these objectives and produced the following key business benefits:
- Reduced number of active mailbox servers by almost 70 percent and associated server
operational costs, resulting in overall messaging cost reduction of at least four
percent
- Maintained user satisfaction and productivity by reducing dependency on real-time
network connectivity
- Created opportunity for further consolidation of distributed sites.
This white paper is for Microsoft customers who are running Microsoft Exchange Server
in a distributed server environment who want to understand how they can benefit
from consolidating the resources in their messaging infrastructure.
The focus of this white paper is on the Microsoft Information and Technology group's
experience in consolidating a large number of Exchange Server 2003 physical
sites into a much small number of RDCs. However, this white paper will also be of
interest to Microsoft customers who are running Exchange Server 5.5 or Exchange Server 2000
in a distributed server environment and are looking to take advantage of the messaging
infrastructure consolation benefits offered by Exchange Server 2003.
This white paper was specifically written for enterprise, business, and technical
decision makers; IT architects; and operations managers who are considering an upgrade
of their messaging infrastructure, or an implementation of a physical site or server
consolidation strategy. It focuses on the needs of the Exchange messaging team who
work in an organization with a physically distributed environment.
Note For security reasons, the sample names of forests,
domains, internal resources, organizations, and internally developed security file
names used in this paper do not represent real resource names used within Microsoft
and are for illustration purposes only.
Introduction
Customers frequently ask Microsoft about the methods employed and lessons learned
when using Microsoft products and solutions in the company. This is where Microsoft
IT serves an important purpose. Not only does Microsoft IT provide traditional IT
functions for the company, but they also act as the company's first and best customer
for each new server and business productivity software release. When an issue is
encountered, Microsoft IT works closely with the Microsoft product development groups
to address the issue.
Prior to the start of the Exchange Server 2003 physical site consolidation
project, the following Exchange messaging team goals had already been achieved:
- Centralization of Exchange Server operations and Microsoft IT help desk functions
during the migration from Exchange Server 5.5 to Exchange Server 2000.
The centralization reduced the number of skilled Exchange administrators required
at each local Exchange site. This was completed in 1999 and 2000.
- In-place upgrade of the individual Exchange Server 2000 servers to Exchange Server 2003.
This was completed in the first quarter of 2002.
The pre-consolidation Exchange messaging environment at Microsoft is illustrated
in Figure 1. Microsoft IT had 118 Exchange mailbox servers deployed into 75 locations.
There were 94 additional Exchange public folder, Internet gateway, and other Exchange
servers deployed to support these sites. Domain controllers, Global Catalog servers,
and file and print servers were also deployed in these locations to support the
local Microsoft employees. Prior to the start of the Exchange Server 2003
physical site consolidation project, all of Microsoft IT's Exchange servers had
been upgraded in-place to Exchange Server 2003. This significantly reduced
the complexity and risk for the physical site consolidation project and provided
a more accurate baseline for comparing pre- and post-consolidation network utilization
and latency as well as user's satisfaction with the messaging service provided by
the RDCs.
.gif)
If your browser does not support inline frames, click here
to view on a separate page.
Figure 1 Pre-consolidation Exchange Server 2003 mailbox
deployment
Pilot physical site consolidations began in the second quarter of 2002 and the worldwide
production consolidation was completed in the first quarter of 2003 – approximately
12 months later.
The post-consolidation Exchange messaging environment is illustrated in Figure 2.
Approximately 75 Exchange server physical sites were consolidated into seven physical
locations. The number of Exchange mailbox servers was reduced by almost 70 percent
from 118 to 36. The key enablers were the extensive use of Windows® Server 2003
and Exchange Server 2003 server clusters and SAN storage solutions coupled
with the new consolidation features in Exchange Server 2003 and Outlook 2003;
and a well-designed Wide Area Network (WAN) topology with capacity to handle increased
messaging traffic.
.gif)
If your browser does not support inline frames, click here
to view on a separate page.
Figure 2 Post-consolidation Exchange Server 2003 deployment
RDCs
A detailed description of the Microsoft pre-consolidation Exchange messaging environment,
the project team organization, and its goals are provided in the Situation section.
For those readers unfamiliar with Exchange Server 2003 and Outlook 2003
physical site consolidation features, a description of this feature set is also
provided.
Related white papers document Microsoft IT's previous experiences with planning,
implementing, and deploying Exchange Server 2003. An extensive list of
white papers can be found at the end of this document. It is assumed that the reader
has basic familiarity with Windows Server™ 2003, Exchange Server 2003,
and Office System 2003 (particularly Outlook 2003).
Although this white paper provides recommendations based on what Microsoft experienced
as an early adopter, it is not intended to serve as a procedural guide. Each enterprise
environment is unique. The plans and lessons described in this white paper need
to be adapted to the specific needs and requirements of each individual organization.
Situation
Microsoft began focusing on consolidating its IT infrastructure in 1999 with the
deployment of Windows 2000 Server, the Microsoft Active Directory® directory
service, and Exchange Server 2000.
Microsoft IT's recent efforts to consolidate Exchange Server 2003 physical
sites represent a major initiative to further optimize the TCO of its enterprise
IT infrastructure while promoting its ongoing strategy to create a model enterprise
IT architecture with a global scope.
Previous Infrastructure Consolidation Efforts by Microsoft
In 1999, Microsoft began one of its largest ever server migrations when it upgraded
its Windows NT® 4.0 server environment to Windows 2000 Server. At the same
time, they deployed Windows 2000 Server Active Directory services in preparation
for the upgrade from Exchange Server 5.5 to Exchange Server 2000.
In total, Microsoft has identified six different approaches for reducing costs through
IT infrastructure consolidation:
- Physical Site
- Server
- Database
- Application and Services
- Operations Management
- Operating Environment
More information on these six different approaches for reducing IT infrastructure
costs through consolidation can be found in Appendix A – IT Infrastructure
Consolidation Strategies Overview.
In 1999, a uniform, across-the-board upgrade from Windows NT Server 4.0 to
Windows Server 2000 and from Exchange Server 5.5 to Exchange Server 2000
reduced infrastructure costs through consolidation of operations management and
operating environments.
The upgrade to Exchange Server 2000 focused on reducing the two key Exchange Server
cost components: help desk costs and operations management costs. In a typical Microsoft
customer organization, these two cost factors together account for 52 percent of
the TCO, according to a META Group TCO study of Exchange 2000 deployments.
Figure 3 shows how these two costs compare with the other annualized cost components
of an Exchange Server 2000 messaging solution in a typical Microsoft customer
environment.
Figure 3 Typical Exchange Server 2000 cost factors
As part of the upgrade from its Exchange Server 5.5 messaging environment to
Exchange Server 2000, Microsoft IT took the proactive step of centralizing
its Exchange messaging operations as well as its internal help desk services to
achieve its first major infrastructure consolidation cost savings.
In 2000 and 2001, Microsoft IT undertook a number of "mini-consolidations" of selected,
small Exchange Server 2000 tail sites where server hardware was close to being out-of-warranty
and there was sufficient WAN bandwidth to support the consolidation of the site
into its nearest neighbor site.
In the second quarter of 2002, Microsoft began its second major Exchange Server
messaging infrastructure consolidation based on the additional consolidation features
available in Exchange Server 2003 and Outlook 2003. Following the
in-place upgrade of the company's existing Exchange Server 2000 servers
to Exchange Server 2003, the Microsoft IT Exchange Messaging team began
its Exchange Server 2003 physical site consolidation project – the
focus of this white paper.
Project Team Members
The deployment of Microsoft IT's Exchange Server 2003 physical site consolidation
at Microsoft involved a number of different groups. The Microsoft IT Exchange Messaging
team led the planning, design and execution of the worldwide physical site consolidation,
working closely with the Exchange Server and Outlook product groups.
Microsoft Information Technology Group
Microsoft IT is responsible for driving global operations and delivering information
technology services to the entire Microsoft organization. The group directs all
activities related to running and maintaining Microsoft information systems worldwide:
technology infrastructure; and corporate and marketing information systems including
production, distribution, and other key internal systems. Microsoft IT works to
provide a world-class utility and excellence in business operations through its
leadership in the design and integration of company strategies, processes, and architecture.
Microsoft IT provides a full range of services including server- and end-user support,
telecommunications management, network operations, and information security. This
role includes managing connectivity for more than 300,000 personal computers worldwide.
Microsoft IT ensures that more than 50,000 employees and 20,000 contractors and
vendors in more than 400 Microsoft locations are able to access corporate network
services and resources 24 hours a day, seven days a week, from around the world.
Because the primary business of Microsoft is software design, Microsoft IT has an
additional responsibility that is unique among global providers. In addition to
running the company's IT utility, Microsoft IT is an early adopter of Microsoft
technologies. They are responsible for testing and deploying Microsoft products
such as Windows Server 2003, Exchange Server 2003, and SharePoint®
products and technologies before these products are released to customers. This
process is known by those within Microsoft as "eating our own dogfood" or simply
"dogfooding."
Dogfooding New Software Releases
In the Microsoft IT "dogfood" messaging environment, servers regularly receive software
patches, Windows Server test releases and upgrades, Exchange server test releases
and upgrades, and more. Each Exchange "dogfood" server is regularly upgraded: twice
a month on average. The changes are implemented to test new scenarios, stress specific
requirements, and continually run the latest application concepts through real world,
enterprise-level production-environment testing. The rate of change in the Microsoft
IT Exchange Messaging environment is very high.
"Dogfooding is a crucial part of the product release cycle. Its part of how we ensure
that our customers get the most reliable, secure and powerful product we can produce.
If we're asking customers to use our products, it's only right that we do so ourselves,
first."
Chris Baker, Group Product Manager
Exchange Server Product Group
Microsoft Corporation
Microsoft IT Exchange Messaging Team
The Microsoft IT Exchange Messaging team comprises the groups listed in Table 1.
Table 1 Exchange Server 2003 Physical Site Consolidation
Project Team
|
Exchange Messaging Group |
Number of People |
Number of People Assigned to the Physical Site Consolidation Project |
|
Program Management |
5 |
1 |
|
Service Management |
5 |
1 |
|
Exchange Client Support |
16 |
2 |
|
Exchange Systems Management |
22 |
5 |
|
System Engineering |
7 |
1 |
|
Exchange Technologists
|
2 |
1 |
|
Senior Manager |
1 |
1 |
|
Total |
58 |
12 |
Site Consolidation Deployment Team
In total, there were 12 people from the Microsoft IT Exchange Messaging team directly
involved in different stages of the Exchange Server physical site consolidation.
In addition to the Microsoft IT Exchange Messaging team, the Exchange Server
product group, and the Outlook product group, other stakeholders in the design,
deployment, and operation of the Exchange Server 2003 physical site consolidation
included the following groups from Microsoft IT:
- Client Services (including the central help desk and approximately 200 regional
IT personnel and account managers)
- Collaboration Services
- Network Connectivity
- Data Center Services
- Identity Management
- Enterprise Application Services
- Security
- Windows Infrastructure Services
Operational Environment
Microsoft employees use e-mail as a primary mode of communication and as a result
place a significant load on the Microsoft IT messaging infrastructure. The average
employee at Microsoft possesses three computers, all of which are typically used
to synchronize with their Exchange server. In addition, a portion of that population
also carries a Pocket PC or Smart phone device that also synchronizes with Exchange.
At Microsoft, the average Remote Procedure Call (RPC) execution rate (measured in
operations per second), is significantly higher than at any other company known
to Microsoft IT. The workload managed by the Exchange servers at Microsoft is typically
more than double the load measured at other companies. The following statistics
help characterize the use of e-mail at Microsoft:
- Global e-mail flow of 11,800,000 messages per day including:
- 8,800,000 average incoming Internet e-mail messages per day — 70 percent of
which are filtered out as either unwanted spam e-mail, virus-infected, or requesting
delivery to invalid e-mail addresses
- Average size of a typical e-mail message is 44 KB
- Approximately 100,000 mailboxes
- The maximum mailbox size was increased from a 100 megabyte (MB) to 200 MB limit
(as part of the physical site consolidation project)
- More than 85,500 distribution groups
- More than 230,000 unique public folders
- 20 databases per server, with 50 gigabyte (GB) maximum database size on new clustered
deployments, and a maximum mailbox size of 200 MB
- Worldwide e-mail delivery in less than 90 seconds, 95 percent of the time
- Backup and restore operation SLA of less than one hour per database
The Microsoft IT server infrastructure includes:
- Clustered mailbox servers employing SAN configurations are scaled per server to
support 2,700 user mailboxes in regional locations and 4,000 user mailboxes in the
headquarters data center.
- Support organization, which supports all Exchange servers worldwide, consolidated
into two centers: Redmond, WA (and Denver, CO for additional user support).
- In addition to the primary corporate Active Directory forest, three additional
forests are used for dogfooding purposes and have Exchange mailbox servers:
- A Level A Test forest, dedicated to running development and test code for Exchange,
operating in a frequently changing Exchange server software environment.
- A specialized Level B Test forest, serving as a limited-use production environment
used by one product division that hosts a limited number of user mailboxes. Specialized
hardware configurations and test scenarios can be run in this environment. Level
B Test uses a two-node server cluster connected to a SAN scaled to support 5,000
user mailboxes.
- A legacy test environment forest, used for testing the compatibility of the previous
versions of the Windows Server operating system versions (specifically Windows 2000
Service Pack-specific testing) with Exchange.
"When talking to customers, it is most often not the software itself that determines
the success of an enterprise infrastructure deployment or upgrade but the way IT
organizations organize themselves and quality of the communication between the IT
teams - particularly between the network operations and e-mail messaging teams.
To be effective, they need to be joined at the hip".
Jed Dawson, Senior Manager
Microsoft IT Exchange Messaging Team
Microsoft Corporation
Microsoft Model Enterprise Initiative
Microsoft IT's initiative to optimize its global investment in IT infrastructure
is known internally as the ME initiative. This initiative began in fiscal year 2002-03
with a Microsoft Operations Framework assessment conducted by an outside consulting
firm.
Like many enterprise IT organizations, Microsoft IT's operational goals are focused
on striking the right balance of availability, performance, flexibility, and cost.
However, Microsoft IT is committed to dogfooding Microsoft products as fully deployed
enterprise solutions before they are released to customers and to using its own
global enterprise infrastructure as a model by which Microsoft customers may benefit.
The ME initiative has the following specific objectives:
- Maximizing the number of management tasks performed centrally (remotely from the
geographically distributed servers and other devices)
- Decreasing the number of sites through the consolidation of the smaller locations
into a smaller number of RDCs
- Reducing the total number of infrastructure and application servers
- Standardizing infrastructure and devices worldwide
Pre-Consolidation Exchange Server 2003 Deployment
When the ME initiative was started, Microsoft IT was supporting over 192 servers
running Exchange Server 2003 on Windows Server 2003 Enterprise
Edition, distributed over 75 locations worldwide. There were 118 dedicated mailbox
servers hosting more than 100,000 mailboxes.
Microsoft IT's strategy has been to deploy infrastructure servers, such as messaging
servers, in dedicated roles for efficient administration. Table 2 shows how Exchange
servers were distributed prior to the Exchange Server 2003 physical site consolidation.
Table 2 Pre-Consolidation Exchange Server 2003 Messaging
Servers
|
Server Role |
Exchange Server 2003 Servers |
|
Mailbox |
118 |
|
Public Folder |
20 |
|
Exchange Routing
|
12 |
|
Internet Gateway |
22 |
|
Dedicated Free/Busy |
6 |
|
Outlook Web Access |
14 |
|
Total Exchange and related servers (excluding co-located domain controllers and
Global Catalog servers) |
192 |
A detailed description of the post-consolidation Exchange messaging environment
is provided in the Solution section of this whitepaper. For those readers unfamiliar
with Exchange Server 2003 and Outlook 2003 physical site consolidation
features, a description of this feature set is provided in the following section.
Understanding Exchange Server 2003 and Outlook 2003
Physical Site Consolidation Features
Microsoft Exchange Server 2003 represents an important, continuing investment
in enterprise messaging solutions by the Microsoft Exchange product group and the
Microsoft IT Exchange Messaging team. Exchange Server 2003 offers several
key improvements required by enterprise messaging and collaboration customers –
including those designing and implementing an infrastructure consolidation strategy.
To understand how Microsoft IT was able to deploy its Exchange messaging worldwide
physical site consolidation solution, it is important to understand the new site
and server consolidation features in Exchange Sever 2003 and Outlook 2003.
"IT managers have been asking us to include these new back-end features -- for clustering,
backup, caching, performance, and more -- into Exchange Server. Exchange Server
2003 has them and we're betting our own business to ensure for our customers that
these new features work easily and well in a very demanding production environment:
ours."
Jerry Cochran, Group Program Manager
Microsoft IT Group
Why Consolidate Exchange Server Sites?
Implicit in most Exchange Server physical site consolidation projects is a
reduction in the actual number of deployed Exchange servers. If the number of the
Exchange Server 2003 servers in a large distributed messaging environment
can be reduced by, for example, 40 servers, the cost savings can be substantial:
- 40 times the software licensing costs
- 40 times installation and operations costs per server for the base hardware and
operating system
- 40 times annual maintenance contract per server on the hardware
- 40 times credit per server for hardware depreciation
- 40 times cost savings for implementation of Exchange Server–specific
updates and service packs per server
In addition, lower TCO is possible because of:
- A reduction in the amount of spare servers and server parts that must be maintained
to meet internal requirements due to the reduced number of servers deployed in the
Exchange Server 2003 environment.
- The redundancy features of Exchange Server 2003 that helped the company
meet more rigorous uptime service level agreements.
- A drop in the acceptable time for system outages because of the implementation of
multiple storage groups and databases per server, which resulted in faster server
recovery.
- Considerably shortened backup time when multiple storage groups and databases were
deployed on each server and the ability to back them up in parallel.
- Simplified system monitoring, such as tracking log events and troubleshooting, was
due to the reduction in the number of servers supported.
In addition to the reduced server-related costs and lower TCO, the following additional
benefits can be realized:
- Single mailbox restore, made possible by using the Recovery Storage Group (RSG)
feature in Exchange Server 2003.
- Near-instantaneous backup and restore without the need to take storage offline using
the Windows Server 2003 Volume Shadow Copy Service (VSS) with Exchange Server 2003.
- Larger mailboxes per user, which are easier to support with Exchange Server 2003
multiple database architecture (and VSS backups).
- A key trade-off is the cost of the increased WAN bandwidth requirements, which can
vary significantly from one geographic region to the next.
Exchange Server 2003 and Outlook 2003 Consolidation
Features
The list of features in Exchange Server 2003 and Outlook 2003 that
enable physical site consolidation and provide for a highly responsive user experience
includes:
- Outlook 2003 Exchange Cached Mode
- Messaging Application Programming Interface (MAPI) compression
- RPC-over-Hypertext Transfer Protocol (HTTP) access
- Buffer packing
- Outlook performance monitoring
- Incremental change synchronization
- Smart change synchronization
- Skip bad items
- Pre-synchronization reporting
- Improved Exchange Server 2003 scalability, clustering and storage management
features
- New Exchange Server 2003 SP1 migration and consolidation tools
Outlook 2003 Exchange Online vs. Exchange Cached Mode
Outlook 2003 Exchange Cached Mode ("cached mode") was originally developed
as an Exchange Server 2003 and Outlook 2003 feature to provide mobile
professionals with more effective offline access to e-mail and address book information
as well as Exchange server access over slow or poor-quality network connections.
It has become the key to providing users in a remote site accessing Exchange servers
in a RDC with the same quality client experience for sending and receiving e-mail
as they would expect from being directly connected to a local Exchange server.
Previous versions of Microsoft Outlook supported offline usage with basic capabilities
for local storage of e-mail messages and the Exchange global address list. Typically,
these features were implemented using real-time RPC transactions to access the user's
local Exchange server. Performance over slow or unreliable links for remote users
was poor.
Cached mode is a new feature of Microsoft Outlook 2003 that is supported by
Microsoft Exchange Server 2003. Cached mode is targeted at providing a
uniform, highly responsive Outlook user experience regardless of the type and quality
of Exchange Server 2003 network connection. This includes high-speed local
network connections, dial-up connections, General Packet Radio Service (GPRS), and
cases when a user is completely disconnected from their Exchange Server.
To achieve this, cached mode supports the local caching of the contents of a user's
Exchange mailbox as well as downloading of a local copy of the offline address list.
Cached mode is the new default configuration setting used by Outlook 2003 when
it connects to an Exchange server.
For enterprise users, the key benefit of cached mode is that it enables remote users
to work with Outlook 2003 over WAN links connected to remote mailbox servers without
suffering the effects of low network bandwidth or high network latency for most
mailbox and offline address list –related operations. The implication for
the network is that high utilization can occur:
- When a large number of people use Outlook 2003 to connect to their Exchange Server 2003
for the first time.
- Many users in a region simultaneously access their regional Exchange servers (for
example, on Monday mornings, the day after national holidays and vacations, or immediately
after large company meetings).
- Outlook 2003 downloads a full copy of the offline address list (due to a substantial
number of new or updated address book records).
The latter can occur because of changes to the Active Directory, such as the additions
of each person's public key infrastructure (PKI) certificate to their user account
or bulk additions or changes due to mergers and acquisitions, telephone area-code
changes, or office moves.
Outlook 2003 users using cached mode perform most of their e-mail –related
tasks from the local mailbox store. This reduces the number of requests to the server
for data and improves user experience for items found in the local mailbox store.
While cached mode works with previous versions of Exchange Server, additional
improvements in compression and performance between Outlook 2003 and Exchange Server 2003
make the user experience even better.
When Outlook 2003 is using cached mode (either by default, by explicitly configuring
it manually, or by using group policy), mailbox items (for example, e-mail messages,
and incoming meeting requests) are downloaded and cached in the Outlook Offline
Store (OST). Other server-supported functions are executed as real-time transactions
against the Exchange server. These include delegate access to another person's mailbox,
querying free/busy information, and access to information stored in Exchange public
folders.
In addition, when Outlook 2003 is configured to download the "no details" offline
address list and an address book entry is opened for display, a real-time, non-cached
access to the user's Global Catalog server is needed to display user profile information
that is not found in the "no details" offline address list. When the full offline
address list is downloaded, a rich set of user profile properties is downloaded.
When Outlook 2003 is configured to download the "no details" offline address
list, only basic name information and e-mail address is cached locally. Any other
requests for user profile information require Outlook to locate and access the user's
Global Catalog server. The specific list of Outlook 2003 address list fields
available in the full and "no details" downloads of the offline address list can
be found in Appendix B.
To determine which Global Catalog server to access, Outlook 2003 sends a request
to the Exchange server. The Exchange server always returns the address of its local
Global Catalog server. If the Exchange server is located in a remote data center,
this may not be the best choice from a network bandwidth and latency perspective.
To address this situation, the address of the closest global address server can
be set explicitly using a registry setting.
MAPI RPC Compression
When using Outlook 2003 and Exchange Server 2003, by default all
content is compressed before being sent from the Exchange server to the Outlook
client and vice versa. This can significantly reduce network bandwidth consumption
between the client and server, depending on the type of message and attachment(s)
sent.
RPC-over-HTTP Access
When used with the Microsoft Windows Server 2003 RPC Proxy Service and
Exchange Server 2003, Outlook 2003 clients can connect simply using
HTTP or Secure Hypertext Transfer Protocol (HTTPS), thereby reducing the need for
virtual private networks (VPNs) or dial-up remote access. If remote users only need
to gain access to corporate messaging information, the IT department does not need
to deploy a VPN infrastructure. VPN-less access reduces costs and provides for increased
security by ensuring that remote Outlook users do not need access to the entire
network. This unifies the connection methods also found in Outlook Web Access and
Outlook Mobile Access.
Buffer Packing
After information is compressed, all information sent from servers running Exchange Server 2003
to Outlook 2003 clients is packaged in larger and more efficient buffer packets,
thereby reducing the number of requests to and from the servers running Exchange.
Outlook Performance Monitoring
Outlook performance monitoring makes it easier for the Exchange systems administrator
to monitor and troubleshoot performance and network connectivity problems. Outlook
collects latency and error information from Outlook clients and sends it to Exchange Server 2003.
This data is held in the Exchange store as well as being recorded in the event log
and performance counters where the data can be accessed by Microsoft Operations Manager
(MOM) 2000. To understand when remote clients are experiencing performance issues
related to poor bandwidth or poor connectivity, interpretation of the Exchange event
log may be performed using the event viewer Microsoft Management Console (MMC) snap-in.
Incremental Change Synchronization
In earlier versions of Microsoft Outlook, when interruptions occurred during the
offline mailbox synchronization process, the entire process had to start over from
the beginning. Incremental change synchronization in Outlook 2003 and Exchange Server 2003
enables the mailbox synchronization process to resume where the outage occurred
instead of starting the entire synchronization process over.
Smart Change Synchronization
In earlier versions of Outlook, the entire message and body was sent to the server.
In Outlook 2003, when items are marked read, unread, flagged, or slightly modified
in other ways, only the header that lists the change is sent back to the server.
Skip Bad Items
During synchronization, items marked as bad or conflicting are now moved to the
Sync Items folder, enabling the synchronization to continue.
Pre-synchronization Reporting
The synchronization progress meter (found in the lower right corner of the Outlook 2003
user interface) shows detailed synchronization information such as new e-mail headers,
total size left to synchronize, and whether the folder is up-to-date.
Improved Exchange Server 2003 Scalability, Clustering
and Storage
Table 3 summarizes the key Exchange Server 2003 features that enable a
larger number of users with larger maximum mailbox sizes to be hosted on an equivalently
configured Windows Server 2003 server.
Table 3 Exchange Server 2003 Scalability Improvements
|
Statistics |
Exchange Server 5.5 |
Exchange Server 2000 |
Exchange Server 2003 |
|
Number of databases |
1 database
|
20 databases
4 storage groups x 5 mail stores each
|
20 database
4 storage groups x 5 mail stores each
5th virtual storage group
|
|
Users per mailbox server |
1,000-2,000 users per server |
3,500-5,000 users per server |
3,500-6,000 users per server |
|
Backup times |
2-3 hours to backup 50 GB database |
2-3 hours to backup 50 GB database |
Near real-time backup using VSS with Windows Server 2003
RSG
|
Recovery Storage Groups
The RSG is a specialized storage group that can exist with regular storage groups.
Although an RSG is similar to a regular storage group, the primary way RSGs differ
from regular storage groups is that all protocols, except MAPI, are disabled. This
means that e-mail cannot be sent to or received from a mailbox store that is in
an RSG. However, use of the Exmerge tool allows access to mailboxes to recover data.
In previous versions of Exchange Server (prior to Exchange Server 2003),
it was necessary to configure a separate Active Directory forest on a recovery
server if another copy or a different version of a production Exchange database
was to be mounted. With the RSG feature in Exchange Server 2003, a separate
recovery computer is not required when data is needed to be recovered from a mailbox
store.
The RSG feature is not intended for use in disaster recovery operations that involve
multiple servers or multiple storage groups. Its intended use is to recover data
from a single mailbox, a single database, or a group of databases that are in a
single storage group. For example, an RSG can be used to recover items that were
deleted and purged from a user's mailbox, or a RSG can be used to restore or repair
a copy of an alternative database while another copy of the database remains in
production.
Improved Cluster Support
Windows Server 2003 provides up to eight-node clustering — an improvement
over the earlier two- and four-node clustering. This new standard allows for better
scalability and availability in a consolidated environment.
Improved Backup and Restore for Very Large Exchange Servers
The other key concerns for IT administrators have been the time, cost, and trouble
of backing up their increasingly large Exchange servers, which can contain up to
500 GB of data on a single server. Exchange Server 2003 supports the VSS
in Windows Server 2003 that allows administrators to mirror a disk in
real time, making it fast and easy to backup.
New Exchange Server 2003 SP1 Migration and Consolidation
Tools
The original Exchange Server 2003 release includes an enhanced version
of the Move Mailbox tool that enables administrators to schedule mailbox moves to
occur automatically at a particular time on a particular day. When used with the
Skip Bad Items feature, this enables Exchange administrators to schedule the automatic
migration of selected groups of users overnight or on weekends without having to
be physically present. In addition, the Move Mailbox tool is now multithreaded,
significantly improving performance.
Exchange Server 2003 Service Pack 1 includes additional new migration
and consolidation tools that are of specific use to Exchange Server 5.5 administrators
who want to migrate from a pure Exchange Server 5.5 environment or an Exchange
mixed-mode environment (a mix of Exchange Server 5.5 and Exchange Server 2000
servers) to an Exchange Server 2003 native mode environment.
Exchange Cached Mode Network Usage
Perhaps the most important aspect of planning for an Exchange Server 2003
physical site consolidation is understanding the differences in network usage that
result when Outlook 2003 changes from locally accessing an Exchange Server
in the pre-consolidation environment to remotely accessing an Exchange Server
deployed in a remote data center in the post-consolidation environment. The two
scenarios are depicted in Figure 4, Figure 5 and Figure 6.
.gif)
If your browser does not support inline frames, click here
to view on a separate page.
Figure 4 Typical pre-consolidation tail site
In the pre-consolidation scenario, all e-mail traffic sent from users at this tail
site to all users outside this tail site must be delivered over the WAN connection
to the Exchange mailbox and public folders servers. All remote public folder access
into or outside this tail site will also flow over the WAN connection. A moderate
level of Global Catalog synchronization traffic is present on the WAN connection
depending on the size of the Active Directory and the frequency and scope of
directory entry changes.
Outlook users access their e-mail and public folders locally across the local area
network (LAN) connection and the user experience is very responsive. In this scenario,
cached mode is only an advantage to mobile users who require a high-quality offline
experience when not connected to their Exchange server. An exception to this is
external users who access their mailbox via Internet VPN connections located in
each RDC.
Figure 5 Typical post-consolidation configuration
.gif)
If your browser does not support inline frames, click here
to view on a separate page.
Figure 6 Typical post-consolidation local office configuration
In this post-consolidation scenario, all Outlook e-mail and public folder traffic
travels over the WAN connection between Outlook users at the local office (former
Exchange tail site) and the Exchange servers running in the remote RDC. In this
scenario, Outlook 2003 is assumed to be configured with cached mode enabled.
The local OST is used to store mailbox and six files are used to store offline address
list (five files for the "no details" option). Again, the exception is external
users who access their mailboxes via the Internet VPN connections located in each
RDC.
All e-mail traffic destined for users in the local office still needs to be delivered
over the WAN connection, although in this scenario a copy of each message will be
downloaded and cached into each user's local OST file. This helps ensure that Outlook 2003
users connecting to an Exchange server in a remote data center will still experience
a high-quality user experience because all of the mailbox and address book information
is stored locally. Real-time transactions across the WAN connection will still occur
for functions such as free/busy information queries, delegate access to another
person's mailbox, and public folder access.
Summarizing the above scenarios, there were five types of network traffic that Microsoft
IT needed to consider:
- Outlook client to/from Exchange mailbox server. Either real-time transactions
or cached mode downloads against a local or remote Exchange server. Real-time transactions
are used for delegate access to another person's mailbox.
- Outlook client to/from Exchange public folder server. Access to information
stored in public folders (including calendar free/busy information) is performed
using real-time transactions against the local or remote Exchange public folder
server.
- Outlook client to/from Global Catalog server. When access to the Global Catalog
server is required, the Exchange mailbox server will return the network address
of its local Global Catalog server to Outlook unless the address has been explicitly
set (overridden) in the user's registry. The choice of whether to download the full
or "no details" offline address list is dependent upon whether the additional items
provided by full details address list, listed in Appendix B, are required by users
when offline.
- Exchange server to/from Global Catalog server. The local or remote Exchange
server makes regular requests of the Global Catalog server that is local relative
to the Exchange server making the request.
- Exchange server to/from Exchange server. With fewer servers concentrated
into a smaller number of physical sites after consolidation, it is possible that
the amount of inter-server traffic will be reduced. In addition, the amount of inter-site
WAN traffic might be reduced depending on the inter-site e-mail traffic pattern.
- Global Catalog to domain controller synchronization. With the removal of
the Exchange mailbox and public folder servers from smaller sites ("tail sites"),
a Global Catalog server may not be required and an additional level of secondary
server consolidation (and corresponding reduction in WAN traffic) may occur.
When the primary consolidation of the Exchange servers in a tail site and the secondary
consolidation of the Global Catalog servers and possibly additional servers occurs,
an organization can also begin to simplify its network infrastructure measured in
terms of the number of dedicated circuits, routers, and switches. However, it is
likely that additional network bandwidth will be required for some links. Depending
on the number of local employees and the bandwidth, cost and quality of ISP-provisioned
Internet access, an organization can choose to further reduce its internal network
costs and complexity by making the local office an Internet VPN connected office.
Given the complexity of the factors that affect network bandwidth utilization and
latency, it is difficult to accurately predict the effects that a large physical
site consolidation will have on the network as well as each user's experience. This
implies that it is difficult to model this environment using simple formulas.
Solution
Having already completed the in-place upgrade of the company's Exchange Server 2000
servers to Exchange Server 2003, the Microsoft IT Exchange Messaging team
set out to identify the strategies and key risks that needed to be considered as
part of the Microsoft worldwide physical site consolidation plan. Three key focus
areas emerged for the Exchange Messaging team:
- Proactive, detailed monitoring and analysis of WAN bandwidth utilization and latency
– before and after consolidating each group of physical sites
- Need for an effective but flexible approach to project planning, scheduling, and
cross-group coordination
- Coordination and control of deployment of successive pre-release versions of Office System 2003
(including Outlook 2003) to the more than 70,000 employee, vendor, and contractor
staff at Microsoft.
Planning
When planning the Exchange Server 2003 physical site consolidation project,
the key parts of the project planning activities included physical site consolidation
strategy, RDC design, Exchange topology design, planning WAN monitoring and measurement,
bandwidth management, and scheduling.
Physical Site Consolidation Strategy
The first prerequisite of undertaking an Exchange Server physical site consolidation
project is that an organization has two or more deployments of Exchange Server
that are separated by slow communications links. In the case of the Exchange messaging
infrastructure at Microsoft, more than 75 sites were candidates for physical site
consolidation.
The second key consideration is where to locate the central and RDCs. This is often
predetermined by the existing physical WAN infrastructure, or in the case of a planned
network upgrade, by new planned or redesigned physical WAN infrastructures. In the
case of the Microsoft Exchange Server 2003 physical site consolidation
project, the location of the RDCs was determined by the overall analysis of IT infrastructure
at Microsoft as well as current and future business needs. This was driven as part
of the Microsoft IT ME initiative.
The third consideration is TCO: do the projected cost savings (excluding WAN cost
increases) outweigh the additional WAN costs?
Lastly, the quality of the network connections and network management processes
to support the consolidated physical site architecture must be in place and network
SLAs sufficient to support the organization's agreed-upon messaging service levels.
Regional Data Center Design
Considerable engineering effort went into designing, building, and testing the Exchange Server 2003
environment deployed into each of the six RDCs. Each RDC Exchange Server configuration
included:
- One clustered Exchange Server 2003 mailbox server using a SAN for mailbox
storage
- Two Exchange Server 2003 front-end servers supporting Outlook Web Access,
Outlook Mobile Access, RPC-over-HTTP and Exchange ActiveSync® access to the back-end
mailbox servers
- Two Exchange Server 2003 public folder servers for user public folder
as well as system folders for storing the offline address list and free/busy calendaring
information
- One or two Exchange Server 2003 Simple Mail Transport Protocol (SMTP)
gateway servers
When this Exchange server configuration was being deployed into the RDCs, existing
Exchange routing servers that were no longer needed were removed from tail sites.
In the RDCs, routing groups were consolidated and larger routing servers were deployed
to handle the consolidated message traffic. Based on the volume of messages, dedicated
routing servers were deployed in some RDCs while in the rest, RDC public folder
servers acted as routing servers.
Exchange Server 2003 gateway servers were upgraded in the RDC locations. All incoming
Internet e-mail continued to be routed through the Redmond data center were each
message was processed by virus defense and junk mail scanners. Exchange Server 2003
gateway servers were deployed in the RDCs for outgoing Internet e-mail enabling
faster delivery of e-mail to local customers and partners.
Similarly, Outlook Web Access and Outlook Mobile Access needed to be upgraded in
each RDC location to handle the larger number of Exchange users being served by
each RDC site.
Multiple public folder servers were used for user public folder storage due to:
- Volume of storage required. The Redmond, WA data center required 400-500 GB of user
public folder storage and there was not enough free storage available on the existing
Exchange SAN.
- User load on a single server would have been too great. Some RDC public folder servers
(which are also used to store free/busy information as well as offline address book
files) are accessed by as many as 15,000 to 20,000 users per day.
The Exchange Server 2003 server and storage hardware to be used in the
RDCs was evaluated and selected by the Microsoft IT Exchange System Engineering
team. The hardware was purchased centrally and shipped directly to each RDC where
it was installed and configured based on the RDC design created by the System Engineering
group.
Each RDC location needed to have more formal and elaborate planning for the power,
HVAC (heating, ventilation, and air conditioning), racking, network cabling and
floor space required by the large RDC server farm and SAN environments.
Exchange System Engineering was also responsible for creating the operating system
and Exchange Server 2003 software image to be installed on each of the
different Exchange Server 2003 servers. Additional staff was required
for extended periods to install, configure, and test the RDC data center environments.
Microsoft IT's largest SAN solutions have required as long as three months from
receipt of the hardware components until they are available for full production
use.
More information on the architecture and design of the RDC server hardware and software
configuration can be found in the Microsoft IT Showcase whitepaper "Exchange Server 2003
Design and Architecture at Microsoft".
Exchange Topology Design
Worldwide, Microsoft has more than 400 offices. All locations are connected by the
Microsoft corporate network, providing each employee location with high-speed access
to services such the Exchange messaging service and the many resources hosted in
the headquarters corporate data center in the Seattle/Puget Sound region.
From a network perspective, the Microsoft IT Network Connectivity team actively
monitors and manages the WAN, which is constructed using a hub-and-spoke topology
with cross-links for redundancy. Fifty percent of the links have a capacity of 2
megabits per second (Mbps) or greater, with most of the circuits operating at either
T1 or E1 speeds. On the low-bandwidth circuits, especially those outside of the
United States, circuit quality, and reliability can vary significantly, depending
on the region and the carrier.
At Microsoft, the percentage of average network bandwidth devoted to e-mail and
related messaging traffic is approximately 10 percent. This relatively low percentage
is due to the disproportionately large amount of non-messaging WAN traffic created
by the Microsoft product development teams.
Virtually all WAN technologies are represented in the current network design including
direct connections, Internet-connected VPNs, Asynchronous Transfer Mode (ATM), frame
relay, point-to-point, and Clear Channel.
As a general policy, Microsoft tries to deliberately ensure that the WAN backbone
links are provisioned to exceed capacity requirements while exercising tight management
on the more expensive bandwidth required to provision tail sites.
On its backbone circuits, Microsoft has worked with its carriers to negotiate the
best possible cost per Mbps in exchange for purchasing larger than normal capacity.
On these backbone circuits, the network traffic created by the product development
groups represents the largest component of the network utilization – not the
traffic generated by Exchange servers or Outlook clients.
In addition to negotiating for a best price, the Microsoft IT Network Connectivity
team also negotiates for specific service levels whose results are reported on the
monthly Microsoft CIO scorecard and regularly reviewed with the WAN carriers. The
Network Connectivity team actively monitors and analyzes WAN performance on each
of its links comparing service levels against a historical database. Packet loss,
latency, and bandwidth utilization for each link are recorded and Microsoft works
actively with its carrier partners to resolve any issues.
Planning WAN Monitoring and Measurement
The Microsoft IT Exchange Messaging team, working with the Exchange Server
product group, wanted to develop a deep understanding of the effects that the Exchange Server 2003
physical site consolidation project would have on the Microsoft WAN. Given the complex
variety of demands placed on the WAN by the Exchange Server messaging and related
services, the changes in bandwidth utilization and latency due to consolidation
is not something that can be modeled by a simple formula or deduced intuitively.
The Microsoft IT Exchange Messaging and Network Connectivity teams developed a network
monitoring and analysis strategy designed specifically to measure the effects of
the Exchange Server 2003 physical site consolidation.
The goal of the Exchange Server 2003 physical site consolidation WAN monitoring
project was to accurately measure the changes in WAN bandwidth utilization that
resulted from consolidating the Exchange Server 2003 tail sites throughout
Microsoft into the six RDCs. For each group of regional tail sites, this included:
- Pre-consolidation tail site preparation
- Pre-consolidation WAN link monitoring (two weeks)
- Migration of mailboxes from a site to the local RDC (one weekend to two-to-three
weeks)
- Post-consolidation tail site preparation
- Post-consolidation WAN link monitoring (two weeks)
Managing Bandwidth Used for Physical Site Consolidation
The rate at which the consolidation of a physical tail site can proceed was limited
by the desire not to affect regular business activities during the business day
and the amount of available bandwidth during the evenings and on weekends. Hence,
initial mailbox migrations were scheduled during the early morning or early evening
when network utilization was low and Exchange Client Services professionals were
available to monitor these mailbox migrations and address any systemic issues. The
bulk of the mailbox migrations from the tail site to the RDC were then scheduled
for the evenings and weekends.
Project Planning and Scheduling
Given that Microsoft IT is most often working with pre-release versions of most
Microsoft software products, one of the most important inputs into a Microsoft IT
project schedule is the product groups' planned internal release dates for the milestone
versions of their products. In the case of the Exchange Server 2003 physical
site consolidation project, the schedule was driven by the release schedules for
Office System 2003, Outlook 2003, and Exchange Server 2003.
The product groups were interested in testing these releases with specific types
of users, network connection speeds, and other scenarios.
The next most important set of inputs into the project schedule was the company's
business requirements such as upgrade blackout periods due to month-end and quarter-end
processing coupled with employee vacation periods. Annual vacations, extended national
and statutory holidays in some countries, as well as weekends, would normally be
optimum times for scheduling mailbox migrations from tail sites to the RDCs. However,
it was important for the pre- and post-consolidation network monitoring that most
employees would be at work with normal workloads for two weeks leading up to the
migration and the two-week period following the migration. The mailbox migration
for a particular group of tail sites would take anywhere from one weekend to three
weeks depending on the number of users and the size of their mailboxes.
Other factors that affected the scheduling of individual tail site consolidations
included:
- Network bandwidth required for mailbox migration. These were usually performed after
business hours or on weekends
- Regional time zones
- Logistics involved in acquiring, configuring, shipping and installing the Exchange
server hardware and software components to each RDC
The largest number of tail sites that Microsoft IT migrated at the same time was
22.
A central project manager coordinated the activities of all the teams involved in
the planning and execution of the physical site consolidation project.
Deployment
The deployment phase of the physical site consolidation followed the project plan
and schedule initially created during the planning phase. The schedule was updated
weekly based on the previous week's progress and the status of any product issues
that had previously surfaced. The primary deployment activities included coordinated
deployment of the appropriate version of Office System 2003 (including
Outlook 2003), RDC build-out, tail site preparation, the actual movement of
mailbox servers to the RDC Exchange servers, and the decommissioning of the tail
site Exchange servers.
Client Deployment
As part of the dogfooding process of testing early pre-release versions of Office System 2003
and Outlook 2003 (with Exchange Server 2003), Microsoft employees
were asked to install each major milestone version of these products. They were
first sent an e-mail with instructions on where and how to install each version
from the local product distribution server in their region. Microsoft employees
feel naturally motivated to install each new version of a product as part of the
extended testing process. Employees know that problems found in their pre-release
versions of a product can be fixed before the product is made generally available
to customers.
For this project, those employees who had not upgraded to the general release of
Office System 2003 and Outlook 2003 by a prescribed date were forced
to upgrade through Microsoft Systems Management Server (SMS), when
they next logged on to their systems. Because SMS is not used on all of the product
group development, consulting services, and technology specialist computers, users
of down-level versions of Outlook 2003 were ultimately locked out from accessing
their Exchange server using a feature built into Exchange Server 2003.
This lockout feature disables MAPI client access to the Exchange Server 2003 server
based on the minimum version of the Emsmdb32 dynamic link library (DLL). Emsmdb32.dll
is part of the Exchange transport service and provides the services that are required
for accessing public folders and your mailbox. Emsmdb32.dll is also involved if
you are working with an offline folder store.
For the bulk of the physical site consolidations, the final release to manufacturing
(RTM) version of Office System 2003 was available and was the prerequisite
version that each Microsoft employee needed to have installed. Having a common version
of Outlook 2003 installed and used by all employees was important from the
point of view of gathering consistent and valid data from the pre-consolidation
and post-consolidation network monitoring tests.
Tail Site Preparation
The goals for pre-consolidation tail site preparation were directly related to the
pre- consolidation and post-consolidation network monitoring goals.
The purpose of the network monitoring activities was to measure network bandwidth
utilization and latency related to a user's direct needs in terms of the Outlook
functionality they use. Hence, the goals of the tail site preparation were to move
specific tail site Exchange services to the RDC prior to the pre-consolidation network
monitoring. The specific Exchange services to be moved were those services, other
than mailbox services, that would not be required in the tail site following the
consolidation of the Exchange services into the RDC. These included, for example,
Exchange SMTP gateway servers, Outlook Web Access servers, and Exchange routing
servers.
As part of the tail site preparation, local user public folders were replicated
to the public folder servers in the RDC to enable the tail site public folder servers
to be quickly decommissioned following the mailbox moves to the RDC and the decommissioning
of the mailbox servers but before the start of the post-consolidation WAN monitoring.
In one scenario, 100 GB of public folder data needed to be replicated, requiring
several weeks for full replication to take place. To reduce the total amount of
public folder replication required, Microsoft IT, working with its local regional
IT representatives, chose to purge public folder data that was more than three years
old.
From a client communications perspective, the Microsoft IT Services Management team
had regular conference calls with the representatives from Client Services regional
IT teams. The regional IT teams in turn would communicate upcoming physical site
consolidation activities to the employees and contractors working in the local region.
Moving User Mailboxes from Tail Sites to Regional Data Centers
The physical mailbox moves were undertaken by the Exchange Client Support team within
the Microsoft IT Exchange Messaging team.
Mailbox Move Support in Exchange Server
Starting with the release of Exchange Server 2000, native-mode Exchange environment
mailboxes can be moved within the same forest without having to backup, delete,
and recreate a user's mailbox. The Active Directory Users and Computers MMC
snap-in is used to move user mailboxes from one server to another in the same site,
or in a different site.
For the physical site consolidation project, the Microsoft IT Exchange Messaging
team created a simple, internal bulk mailbox move tool that reads a list of users
and Exchange servers from a file and creates five parallel threads to move as many
as five users' mailboxes at a time. The Messaging team used the bulk mailbox move
tool in addition to the Users and Computers MMC snap-in.
With Exchange Server 2000, if a mailbox has a corrupted item, the mailbox cannot
be moved until it was fixed with the Exchange Server Exmerge tool. This reduced
the productivity of the Microsoft IT Exchange Client Support staff and represented
a potentially huge problem when a large number of mailboxes needed to be moved.
With Exchange Server 2003, the Active Directory Users and Computers
MMC snap-in supports a feature called Skip Corrupted Items. This feature makes it
possible to manually move a mailbox even if it contains corrupt items. When the
bulk mailbox move tool failed to move a mailbox, the incident would be logged as
a service request and was most often resolved using the Active Directory Users
and Computers MMC snap-in with Skip Corrupted Items enabled.
This overall approach greatly improved the productivity of the Microsoft IT Exchange
Client Support staff by allowing them to plan to move 100 and up to 200 mailboxes
per day from each tail site to an RDC. They were able to do this without having
to continuously monitor the process for failures due to corrupted mailbox items.
As part of the mailbox move process, the Exchange Client Support team also needed
to update each employee's unified messaging configuration, which allows incoming
voice mails to be received as e-mails in the employee's personal mailbox.
Physical Site Consolidation Project Mailbox Moves
The overall communications plan to the employees was managed by the Service Management
team. Coordination across all of the teams was handled by the program management
and service management teams in the Microsoft IT Messaging group.
The actual mailbox moves were scheduled to be executed in bulk using Microsoft IT's
internal bulk mailbox move tool. The bulk mailbox move tool read a file containing
a list of accounts to be moved and calls the same Exchange Server mailbox move
Application Programming Interface (API) used by the Active Directory Users
and Computers MMC snap-in. Approximately 100 to 200 tail site mailboxes were migrated
per day from each tail site. The mailbox moves were scheduled to run in the evening
based on the tail site's local time.
All problems that occurred during the mailbox moves were logged and addressed by
the Microsoft IT Exchange Client Support team who would triage, troubleshoot, and
resolve each issue as required. In many cases, the problem was resolved using by
manually moving the mailbox using Active Directory Users and Computers MMC
snap-in with Skip Corrupted Items enabled.
Special attention was given to tail site mailbox moves where there was a high failure
rate (affecting greater than 10 to 15 percent of the tail site's mailboxes) indicating
a more serious issue (such as a problem with one of the mailbox server storage groups).
Server-level issues required the involvement of other Exchange Messaging teams within
Microsoft IT. These teams were coordinated by the Exchange Client Services project
manager.
Approximately 10,000 mailboxes were moved from tail site Exchange servers to Exchange
servers in the RDCs. The remaining 45,000 employee mailboxes were not affected by
the Exchange Server 2003 physical site consolidation project because these
mailboxes were on Exchange mailbox servers that were already part of one of the
six RDCs.
Decommissioning Exchange Site Servers
Once the most critical step of moving users' mailboxes from the mailbox server in
a tail site to the mailbox server in the RDC was complete, the next important step
for Microsoft IT was the orderly decommissioning of the Exchange servers in each
tail site. In general, there were two common tail site configurations that needed
to be addressed as shown in Figure 7:
- Single Exchange server tail sites that used a single server to provide both mailbox
and public folder services (including free/busy information); and
- Dual Exchange server tail sites where separate servers were used for mailbox services
and public folder (and free/busy) services.
.gif)
If your browser does not support inline frames, click here
to view on a separate page.
Figure 7 Common Microsoft IT tail site configurations
To decommission each of the two tail site configurations, there were two alternatives:
1) decommission the mailbox servers first, or 2) decommission the public folder
servers first (including the offline address list and free/busy server). Microsoft
IT chose to begin the decommissioning the public folder servers before site consolidation
to eliminate as much tail site WAN traffic as possible and enable more accurate
pre-consolidation monitoring and measurement of network bandwidth utilization and
latency.
To prepare for the decommissioning of the public folder server in a tail site, Microsoft
IT made sure that all user public folders had replicas on an RDC public folder server
(or that the appropriate replicas were created where necessary). This enables the
tail site public folder servers to be decommissioned immediately after the tail
site mailbox moves were completed and before post-consolidation WAN monitoring was
started. Full replication of a large public folder structure may take several hours,
days, or even weeks depending on the amount of information in the public folders
and the saturation of the WAN connection between the tail site and the RDC. This
migration was scheduled to occur outside regular business hours.
After a mailbox is moved from a tail site to an RDC mailbox server cluster, Exchange
Server automatically updates a user's Outlook profile to point to the new mailbox
server the first time Outlook tries to connect to its old mailbox server following
the mailbox move. For this reason, it is helpful to leave the tail site mailbox
running as long as is reasonable after the mailboxes have been moved to the RDC
to accommodate users who may be away on vacation. Otherwise, some users will have
to manually reconfigure their profiles to point to the new RDC mailbox server. In
the case of Microsoft IT's physical site consolidation project, the tail site mailbox
servers were decommissioned as soon as the mailboxes had been successfully migrated
to the RDC mailbox servers to allow accurate post-consolidation monitoring to occur
as soon as possible, without any extraneous tail-site Exchange server traffic interfering
with the network traffic results.
While not formally part of this project, secondary consolidation of selected Global
Catalog servers and other servers was also made possible.
Operational Considerations
Once the physical site consolidation had commenced (and was subsequently completed),
the operational focus was shifted to managing the six RDCs and continuing to monitor
and gather network bandwidth utilization and latency statistics on each WAN segment
used to connect the RDCs.
Planning for RDC Upgrades
Prior to the Exchange site consolidation project, the Exchange servers in the local
tail sites require periodic upgrades as new employees were hired. It was a relatively
straightforward, incremental process: a "small" server would be upgraded to a "medium"
server, and a "medium" server to a "large" server. Once upgraded, the server would
have enough capacity to support the hiring of several dozens to several hundreds
of new employees.
With the smaller number of RDC-based large Exchange server farms, Microsoft IT has
found that upgrading planning has become a more demanding process. Some RDCs are
growing annually by more 1000 users (including employees and contractors). These
types of growth rates require more planning effort and different levels of approvals
given that these are not conventional single server upgrades. SAN storage may have
to be increased; Outlook Web Access and Exchange Server 2003 gateway servers may
have to be upgraded. Planning for online backup services (provided by a different
organization within Microsoft IT) is similarly affected.
Microsoft IT has begun planning for the eventual time when maintenance and warranty
programs on its large SANs will expire and replacement systems will need to be purchased.
SANs are significantly more complex that the single servers removed from the tail
sites. More pre-sales configuration and planning is required; longer delivery times
are required.
Upgrades to consolidated servers and sites tend to be in larger increments than
those experienced with tail site upgrades; requiring more engineering, budgeting
and deployment planning.
Resolution of Outstanding Issues
As part of its dogfooding effort, Microsoft IT worked with the Exchange Server
product group to reduce the network bandwidth usage for downloading the full offline
address list. Frequent changes occur at Microsoft due to personnel relocations (requiring
cross-forest mailbox moves) and external factors such as area code changes that
cause bulk changes that affect many directory entries. When a sufficiently large
number of changes occur, this triggers the download of the full offline address
list over the network to each Microsoft employee's personal computer(s). Given the
large number of entries in the Microsoft IT enterprise Active Directory, the
compressed size of the downloadable offline address list was 50-60 MB in size.
This is an example of the dogfooding process at work within Microsoft IT and the
Microsoft product groups to test and resolve these types of issues as early as possible
in a live, worldwide production enterprise environment.
Conclusions
Through consolidation, Microsoft IT was able to reduce the number of Exchange Server 2003
physical sites from 75 to seven physical sites and the number of physical mailbox
servers from 118 to 36. The results of its successful Exchange Server 2003
physical site consolidation project are shown in Table 4.
Table 4 Reduction in Microsoft IT Exchange Servers
|
Server Role |
Pre-Consolidation |
Post-Consolidation |
|
Mailbox |
118 |
36 |
|
Public Folder |
20 |
11 |
|
Exchange Routing |
12 |
13 |
|
Internet Gateway |
22 |
19 |
|
Dedicated Free/Busy |
6 |
0 |
|
Outlook Web Access |
14 |
11 |
|
Cluster Passive Nodes |
0 |
24 |
|
Total Number of Servers |
192 |
114 |
In total, approximately 10,000 mailboxes were moved from 75 tail sites to six RDCs,
and a significant network bandwidth issue related to offline address list full downloads
was identified. It recommended that customers read the following Knowledge Base
article http://support.microsoft.com/default.aspx?scid=kb;en-us;839826
for more details on how to address this issue.
Microsoft IT was able to leverage the new storage, scalability, and recoverability
features in Exchange Server 2003 and Windows Server 2003 to
increase the number of mailboxes deployed per Exchange mailbox server by 33 percent
to approximately 4,000 mailboxes per server. At the same, they increased the server
mailbox size from 100 MB under Exchange Server 2000 to 200 MB under Exchange Server 2003,
as shown in Table 5.
Table 5 Microsoft IT Exchange Messaging Statistics
|
Statistics |
Exchange Server 2000 |
Exchange Server 2003 |
|
Mailboxes per server |
3,000 |
4,000 |
|
Mailbox size per user |
100 MB |
200 MB |
|
Restore time per database |
~1 hour |
~25 minutes |
|
Total number of mailboxes |
~71,000 |
~85,000 |
|
Maximum storage required |
~7 terabytes |
17 terabytes |
With significant increases in the total amount of storage deployed per mailbox server,
the ability to restore an Exchange mailbox in a disaster recovery scenario becomes
critically important. In any of the RDCs, Microsoft IT is able to restore an Exchange Server 2003
database in approximately 25 minutes, less than half the time it took with the Microsoft
Exchange 2000-based messaging environment.
Business Benefits
Microsoft was able to realize two key business benefits from this project:
- Four percent overall direct cost savings from the Exchange Server 2003
physical site consolidation
- The Exchange physical site consolidation project was a key enabler and integral
part of the Microsoft ME initiative, which through fiscal year 2003 has produced
$23.2 million US in overall consolidation savings including $18.3 million in additional
datacenter consolidation savings.
The overall cost savings were driven by reductions in messaging operations staff.
Prior to the Exchange Server 2003 deployment, Microsoft IT's messaging operations
were already highly centralized, with central support representing 94 percent of
the staff costs. Operating efficiencies from the Exchange Server 2003 deployment
included a further 14 percent overall staff reduction by eliminating 33 percent
of the remaining regional staff support and reducing central staff by 11 percent.
Allocated bandwidth costs increased seven percent due to increased WAN utilization,
but because messaging traffic represents a small percentage of overall Microsoft
bandwidth usage, no actual increased system capacity was required specifically for
the Exchange Server 2003 deployment. The overall cost savings do not include any
hardware savings because Microsoft opted to increase e-mail messaging service levels
(for example, increased mailbox size and system reliability) as part of the Exchange
Server 2003 physical site consolidation project.
IT Benefits
Microsoft IT was able to derive the following benefits from the Exchange Server 2003
physical site consolidation:
- Improved server utilization by maximizing every server's storage capacity, processor,
and memory resources.
- Improved server management by reducing the number of servers which in turn reduced
the time spent on maintaining operating systems and applications, backing up data,
and deploying new applications; and by reducing the need for highly skilled IT staff
in different geographical areas.
- Strengthened security by removing points of vulnerability and streamlining security
management.
- Increased reliability by enabling tighter management practices required for high
availability and reducing exposure to theft, accidental damage, and natural disasters.
Best Practices and Lessons Learned
Since Microsoft IT is a leading-edge implementer of Microsoft technologies and products,
the organization brings a unique set of requirements as well as innovative approaches
to meeting the needs of its internal customers.
Executive Sponsorship
As is the case for many large infrastructure projects, executive sponsorship at
the CIO level was critically important from both a funding perspective; but also
to ensure that the common vision, strategy and set of priorities represented by
the Model Enterprise initiative were followed.
Budget Planning
Large Hardware Upgrade Considerations
For this Exchange site consolidation project, Microsoft acquired all of the upgraded
servers and SANs for the RDC in the same fiscal year. The downstream implication
is that three years from the initial hardware deployment, the hardware will need
to be refreshed or the warranty programs extended for an additional one to two years.
The ability to stagger large hardware refreshes over multiple years is one strategy
Microsoft IT is considering.
Hardware Warranty Considerations
Extended warranty costs was an important factor in determining the pace for consolidating
and decommissioning of tail site hardware; especially in regions where 24-hour daily
support is required and where additional costs are incurred for this level of service.
Team Organization
Cross-Organization and Cross-Functional Teams Involved from the Beginning of the
Project
The Microsoft IT Exchange Messaging team established a cross-organization team that
represented the needs of all aspects of the Exchange Server 2003 physical
site consolidation; including teams from outside the Exchange Messaging team itself.
Representatives were involved in the first planning stages of the project, even
if their actual involvement was not required until much later in the project. Says
one team member, "With no representative, you don't have a vote."
Service-Oriented IT Organization Structure
Look at the integrated, end-to-end delivery of business services. Avoid adopting
an organization structure that is oriented around technology services, such a file
services, printer services, and directory services. For example, during the previous
upgrade from Exchange 5.5 to Exchange 2000, Microsoft IT, like all Windows 2000
Server and Exchange 2000 Server customers, needed to design and deploy Active Directory
services. This group, which initially focused on directory services as a necessary
technology, is now responsible for all aspects of identity management at Microsoft,
including secure smart card employee badges.
Communications
Looking back on the overall Exchange Messaging team experience since 1999, it was
important to combine or otherwise ensure direct and open communication between the
directory (identity management) and e-mail messaging teams in the early stages of
upgrading from Windows NT Server 4.0, Active Directory services,
and Exchange Server 5.5 to later versions of Windows Server.
Once Active Directory services and later versions of Exchange Server had
been fully deployed, the Microsoft identity and directory services management team
was established as a separate entity to address the growing needs within Microsoft
for identity and directory services management.
Project Planning, Scheduling, and Coordination
Project Management Office
Coupled with best practice of creating cross-organizational and cross-functional
project teams is the need for a project manager or project management office that
acts as a common point of scheduling and coordination for the whole project team.
Similarly, a prerequisite for a successful organizational and cross-functional project
team is a common, integrated project plan that is accessible to all members of the
team.
Deployment Scheduling
A critical factor for the Microsoft IT Exchange Messaging team's success with the
Exchange Server 2003 physical site consolidation was the creation of a
detailed yet flexible schedule for building, testing, and releasing the Exchange Server
environments in the RDCs, and coordinated scheduling of each element of the tail
site migration to the RDC. At a high level, this included the following steps:
Pre-consolidation tail site preparation:
- Pre-consolidation WAN link monitoring (two weeks)
- Migration of mailboxes from a site to the local RDC (one weekend to two-to-three
weeks)
- Post-consolidation tail site preparation
- Post-consolidation WAN link monitoring (two weeks).
Other best practices included: creating schedule buffers to allow the migration
teams enough time to clean up loose ends and to prepare for the next phase of tail
site migrations; being very much aware of the challenges (and opportunities) represented
by end-user vacations, instead of focusing only on migration team vacations; national
and statutory holidays; and upgrade blackout periods due to business restrictions
and similar events.
Outlook 2003 Client Deployment
Use an approach that works best for your organization and your employee culture.
Where possible, use an automated desktop management and application deployment solution
like SMS. In addition, keep the following lessons in mind:
- Take into account effective geographic distribution of installation file servers
for Outlook 2003 global deployments.
- Plan for the effect of propagating a large package.
- Locate distribution file servers for most efficient use of network links between
users and these servers.
Network Planning
Given that Microsoft IT had no previous experience with the new site and server
consolidation features in Exchange Server 2003 and Outlook 2003,
extensive WAN monitoring was undertaken, both before and after the consolidation
of each tail site into the appropriate regional RDC. The lessons learned by the
network monitoring team included:
- Recognize that there are no simple formulas for predicting the changes in WAN bandwidth
utilization when consolidating the servers and services in a global enterprise messaging
environment.
- Ensure there is reasonable bandwidth available to support mailbox moves (and potential
public folder synchronization for migrating tail site public folders to an RDC).
- Ensure there is sufficient bandwidth to support the aggregate requirements of tail
site Outlook users after the physical site consolidation is complete.
- Beware of the bandwidth requirements needed to transfer the network monitoring data
to a central site for analysis.
- Gather and maintain a historical base line of WAN utilization and latency data as
well as Exchange related statistics such message deliver times between pairs of
representative global office locations.
- Gather WAN utilization and latency data for as long as is feasible before and after
each tail site consolidation to account for people on vacations and unexpected periods
of low network usage as well as portion of Exchange vs. non-Exchange network traffic.
- It was important to have specific network monitoring data available for the times
when some users questioned the responsiveness of accessing their Exchange services
after the services have been consolidated into an RDC.
- Beware of large infrastructure changes such as Active Directory changes (area code
changes and addition of cell phone numbers for a large number of employees) through
effective cross-team communications.
Summary
Prior to deploying its physical site consolidation solution, Microsoft IT used pre-release
versions of Microsoft Exchange Server 2003 and Office System 2003
to upgrade its existing Exchange Server 2000 messaging platform. Microsoft
IT then undertook the deployment of its physical site consolidation solution to
reduce the number of physical locations running Exchange Server from 75 to
seven physical sites (six RDCs plus one Exchange site in Johannesburg, South Africa).
The objectives achieved by the Exchange Server 2003 physical site consolidation
included:
- Consolidation of the number physical locations running Exchange Server from
75 to seven physical sites (six RDCs plus one Exchange site in Johannesburg, South
Africa).
- Accurate monitoring, gathering, analysis, and reporting of changes in network bandwidth
utilization and latency.
- Measurement any perceived changes in Microsoft employees' Outlook client user experience.
- Detailed analysis of the attendant reduction in annualized costs associated with
the reduction in the number of Exchange Server physical sites.
- Documentation Microsoft IT's Exchange Server physical site consolidation experiences,
best practices, and new lessons learned for the benefit of Microsoft customers.
The Exchange Server 2003-based physical site consolidation solution by
the Microsoft IT produced the following key business benefits:
- Reduced number of active mailbox servers by almost 70 percent and associated server
operational costs, resulting in overall messaging cost reduction of at least four
percent.
- Maintained user satisfaction and productivity by reducing dependency on real-time
network connectivity.
- Opportunities for additional consolidation of distributed sites.
For More Information
For more information, please refer to the following resources.
Microsoft IT Showcase White Papers and Case Studies
Microsoft Exchange Server 2003
- Kay Unkroth,
Server Consolidation Using Exchange Server 2003, Microsoft Corporation,
February 2004.
- Microsoft Exchange Product Group,
Business Value of Microsoft Exchange Server 2003, Microsoft Corporation,
March 2004.
- Microsoft Services,
Beyond Cost Reduction to Higher Business Value: How consolidating servers can reduce
the total cost of ownership, Microsoft Corporation, 2003.
- Joey Masterson,
Exchange Server 2003 RPC over HTTP Deployment Scenarios, Microsoft
Corporation, January 2004.
- Exchange
Server 2003 ROI Evaluation Report, Nucleus Research Inc., 2003.
- Matt Cain, E-Mail:
at What Cost, parts 1 and
2, META Group, 17 Jan 2002.
-
Exchange Server 2003 Service Pack 1, Microsoft Corporation, June 2004.
Microsoft Office Outlook 2003
Microsoft Knowledge Base Articles
- "How to configure how the Offline Address Book is downloaded when you use Outlook 2003
in Exchange Cached Mode" (KB Article
823580), Microsoft Corporation, January 2004.
- "High network usage occurs while Outlook clients download the Offline Address Book
from Exchange Server 2003 at the same time" (KB
Article 839826), Microsoft Corporation, April 2004.
- "Modify Remote Procedure Call Compression in Exchange Server 2003" (KB
Article 825371), Microsoft Corporation, August 2003.
- "Feature to Disable MAPI Client Access" (KB
Article 288894), Microsoft Corporation, November 2003.
Microsoft Sales Information Center
For more information about Microsoft products or services, call the Microsoft Sales
Information Center at (800) 426-9400. In Canada, call the Microsoft Canada information
Centre at (800) 563-9048. Outside the United States and Canada, please contact your
local Microsoft subsidiary. To access information via the World Wide Web, go to:
http://www.microsoft.com
http://www.microsoft.com/services/microsoftservices/howmsdoesIT.mspx
http://www.microsoft.com/technet/itsolutions/msit/default.mspx
http://www.microsoft.com/exchange/default.mspx
For any questions, comments, or suggestions on this document, or to obtain additional
information about Microsoft IT Showcase, please send e-mail to:
showcase@microsoft.com
Appendix A - IT Infrastructure Consolidation Strategies Overview
To fully understand Microsoft IT's deployment of its Exchange Server 2003
physical site consolidation solution, it is important to understand the different
approaches to IT infrastructure consolidation.
There are six basic options available to organizations that wish to consolidate
a highly distributed enterprise computing infrastructure. Implementing these infrastructure
consolidation options can create significant opportunities for long-term infrastructure
improvements and increased operational flexibility. These six infrastructure consolidation
options include:
- Physical site
- Server
- Data
- Application and services
- Operations management
- Operating environment.
Implementation of each of these consolidation options can return significant, measurable
increases in efficiency, productivity, and cost benefits in organizations that have
deployed a highly distributed server infrastructure by reducing server hardware
and software costs; reducing the number of systems administration, monitoring, and
maintenance staff; and increasing reliability, availability, security, and performance.
Additional information can be found on the
Microsoft Business and Technology Center web site.
Physical Site Consolidation
Physical site consolidation refers to reducing the physical number of locations
where server resources reside. The benefits of physical site consolidation include:
- Improvement of both physical and system security because there are fewer components
to setup, configure, and manage and fewer locations where this occurs.
- Reduced backup and storage costs because it is more efficient and less costly to
backup a smaller number of larger capacity servers.
- Reduced systems management and update costs because there are a smaller number of
individual servers and site locations that have to be managed.
- Enabling of a service infrastructure that can support fluctuations in staff, services,
and business processes that is made possible by the larger economies of scale inherent
in larger regional sites.
An example of physical site consolidation is the migration of Exchange messaging
services from a highly distributed, branch office-based deployment to a significantly
smaller number of RDCs. To fully realize the benefits of physical site consolidation,
the set of applications and services need to support consolidation at the server
level.
Server Consolidation
Server consolidation is the result of reducing the total number of individual servers
for a particular application in a single physical site or across multiple physical
sites (due to site consolidation). The resulting benefits include:
- Improved utilization of disk storage, backup, and processing capacity
- Increased effectiveness of high-availability and capacity management solutions
- Simplified service management and maintenance costs
- Reduced fees for server licenses
- Easier integration of applications and services with other data center services
A key requirement for server consolidation is that the application and services
software platform needs to support a significantly increased number of users while
maintaining both an acceptable user experience and service levels related to processing
levels, backup and restore, and other data management tasks.
Data Consolidation
Combining data from multiple databases into a single repository is another approach
to consolidating infrastructure resources and reducing the total cost of ownership.
The benefits of data consolidation include:
- Reduced storage management costs
- Simplified backup and disaster recovery management
- Minimized duplicate data and improved access to business data
- Improved data integrity through more reliable storage systems and more rigorous
data maintenance procedures
A practical example of data consolidation is the consolidation of the number of
data storage servers in a front-end/back-end or multi-tier application.
Application and Service Consolidation
When possible, consolidating multiple different services and applications on fewer
servers can:
- Increase utilization of existing servers
- Improve the scalability of applications
This option is applicable when there is a set of compatible applications and services
that can be configured to run together at the same, or possibly larger, server.
Operations Management Consolidation
In some highly distributed server environments, many organizations often deploy
additional IT operations staff to provide local operations and help desk support.
Supporting a large distributed environment with a large distributed team of skilled
operations staff is often difficult. The benefits include:
- Reduced number of remote server operations and help desk personnel
- More consistent service levels for remote sites
Remote administration features are the key prerequisites for centralizing operations
management functions and staff, and reducing the number of operations staff required
in remote locations. Without an effective way to remotely manage a set of applications
and services, local operations staff will continue to be required.
Operating Environment Consolidation
Standardizing on fewer versions of the same operating systems can:
- Simplify service management and maintenance costs
- Increase utilization of existing servers
The larger the number of server operating systems and operating system versions
that are in concurrent use, the greater the costs will be to support the overall
environment. More importantly, a diverse operating environment is a key obstacle
to effective application and service, data, server, and physical site consolidation.
Overall Infrastructure Consolidation Benefits
TCO is still the most compelling reason to consolidate. By some accounts, server
management and support costs can amount to as much as 80 percent of IT spending,
fueling the need for a well-conceived server consolidation project and the enormous
business value that accompanies it. Overall infrastructure benefits include:
- Improved server utilization by maximizing every server's storage capacity, processor,
and memory resources.
- Improved server management by reducing the number of servers which in turn reduced
the time spent on maintaining operating systems and applications, backing up data,
and deploying new applications; and by reducing the need for highly skilled IT staff
in different geographical areas.
- Strengthened security by removing points of vulnerability and streamlining security
management.
- Increased reliability by enabling tighter management practices required for high
availability and reducing exposure to theft, accidental damage, and natural disasters.
Appendix B – Offline Address List Fields: Full Download vs.
No Detail Download
The following fields are downloaded with the "no details" offline address list:
|
"No Details" Offline Address List Fields |
|
ACCOUNT |
|
DISPLAY_NAME |
|
EMAIL_ADDRESS |
|
POFFICE_LOCATION |
|
SMTP_ADDRESS |
|
SURNAME |
The following additional fields are downloaded with the Full offline address list:
|
Additional Full Download Offline Address List Fields |
|
ASSISTANT |
|
ASSISTANT_TELEPHONE_NUMBER |
|
BUSINESS_TELEPHONE_NUMBER |
|
BUSINESS_TELEPHONE_NUMBER |
|
BUSINESS2_TELEPHONE_NUMBER |
|
COMMENT |
|
COMPANY_NAME |
|
COUNTRY |
|
DEPARTMENT_NAME |
|
EMS_AB_HOME_MDB (Unicode offline address list only) |
|
EMS_AB_PROXY_ADDRESSES |
|
EMS_AB_TARGET_ADDRESS (Unicode offline address list only) |
|
EMS_AB_X509_CERT |
|
GIVEN_NAME |
|
HOME_TELEPHONE_NUMBER |
|
HOME2_TELEPHONE_NUMBER |
|
INITIALS |
|
LOCALITY |
|
MOBILE_TELEPHONE_NUMBER |
|
PAGER_TELEPHONE_NUMBER |
|
POSTAL_CODE |
|
PRIMARY_FAX_NUMBER |
|
STATE_OR_PROVINCE |
|
STREET_ADDRESS |
|
TITLE |
|
USER_CERTIFICATE |
|
USER_X509_CERTIFICATE |
The information contained in this document represents the current view of Microsoft
Corporation on the issues discussed as of the date of publication. Because Microsoft
must respond to changing market conditions, it should not be interpreted to be a
commitment on the part of Microsoft, and Microsoft cannot guarantee the accuracy
of any information presented after the date of publication.
This White Paper is for informational purposes only. MICROSOFT MAKES NO WARRANTIES,
EXPRESS, IMPLIED, OR STATUTORY, AS TO THE INFORMATION IN THIS DOCUMENT.
Complying with all applicable copyright laws is the responsibility of the user.
Microsoft grants you the right to reproduce this White Paper, in whole or in part,
specifically and solely for the purpose of personal education.
Microsoft may have patents, patent applications, trademarks, copyrights, or other
intellectual property rights covering subject matter in this document. Except as
expressly provided in any written license agreement from Microsoft, the furnishing
of this document does not give you any license to these patents, trademarks, copyrights,
or other intellectual property.
Unless otherwise noted, the example companies, organizations, products, domain names,
e-mail addresses, logos, people, places, and events depicted herein are fictitious,
and no association with any real company, organization, product, domain name, e-mail
address, logo, person, place, or event is intended or should be inferred.
© 2004 Microsoft Corporation. All rights reserved.
Microsoft, Active Directory, Outlook, SharePoint, Exchange, Windows, Windows
NT, and Windows Server are either registered trademarks or trademarks of Microsoft
Corporation in the United States and/or other countries.