Lab Preparation Task List

Table 4.2 summarizes the tasks you need to perform when designing and building a test lab.

Table   4.2 Lab Preparation Task List

Task

Location in Chapter

Select a lab model.

Determining the Lab Strategy

Select one or more lab locations.

Determining the Lab Strategy

Set up an interim lab (if needed).

Setting Up a Preliminary Lab

Determine lab space and environmental requirements.

Designing the Lab

Determine power and network connection requirements.

Designing the Lab

Design and document logical and physical configuration for the lab.

Designing the Lab

Determine hardware requirements.

Designing the Lab

Determine software requirements, including business applications and tools.

Designing the Lab

Determine who needs to use the lab.

Designing the Lab

Determine database requirements.

Designing the Lab

Determine wiring and network tap plans.

Designing the Lab

Acquire hardware, including cables and software.

Building the Lab

Acquire workspace equipment, such as desks, chairs, whiteboards, corkboards, lamps, telephones, and shelving.

Building the Lab

Build and configure the network.

Building the Lab

Test network connectivity.

Building the Lab

Build and configure the servers.

Building the Lab

Install applications and build databases on the servers.

Building the Lab

Install testing and administrative tools.

Building the Lab

Build and configure the client computers.

Building the Lab

Install applications on the client computers.

Building the Lab

Test all the lab components.

Building the Lab

Assign a lab manager.

Managing the Lab

Define a change control process for the lab.

Developing Lab Guidelines

Create, test, and document the lab restore process.

Developing Lab Guidelines