Export (0) Print
Expand All

Precedence Constraint Editor

Use the Precedence Constraint Editor dialog box to configure precedence constraints.

Evaluation operation

Specify the evaluation operation that the precedence constraint uses. The operations are: Constraint, Expression, Expression and Constraint, and Expression or Constraint.

Value

Specify the constraint value: Success, Failure, or Completion.

NoteNote

The precedence constraint line is green for Success, red for Failure, and blue for Completion.

Expression

If using the operations Expression, Expression and Constraint, or Expression or Constraint, type an expression. The expression must evaluate to a Boolean.

Test

Validate the expression.

Logical AND

Select to specify that multiple precedence constraints on the same executable must be evaluated together. All constraints must evaluate to True.

NoteNote

This type of precedence constraint appears as a solid green, red, or blue line.

Logical OR

Select to specify that multiple precedence constraints on the same executable must be evaluated together. At least one constraint must evaluate to True.

NoteNote

This type of precedence constraint appears as a dotted green, red, or blue line.