Streamlining Your Application Analysis and Testing Project
What’s our next project? Test our applications to get ready
for Windows 7? No problem, boss. We just have about 950 that we need to look
at…
How thoroughly you’ve conducted the application compatibility
portion of the migration project will determine if your OS roll-out is
reasonably smooth, or if you’re about to throw your IT team into a firestorm of
help-desk calls, finger-pointing and numerous late nights.
When companies began evaluating Windows Vista a few years
back, application compatibility was the issue that stopped some dead in their
tracks. In many of these cases, critical
applications an organization relied upon for key business functions simply were
not available for Windows Vista. In
other cases, organizations did not have the budget, nor desire, to license the
new version that was designed for Windows Vista. Finally, in some instances, key applications
were custom or in-house development efforts where the original developers were
either no longer around or otherwise not available to re-engineer the code
base.
If you are looking to migrate to Windows 7, you’ll find the
situation isn’t as challenging as it was a few years back—most applications
designed to work with Windows Vista will work fine with Windows 7, and most
ISVs have updated their applications to work with this new generation of
Windows operating system. So whether
you’re migrating from Windows XP or Windows Vista, the situation isn’t quite as
tough as it was in the past.
That said, getting your application portfolio ready for an
OS migration can be a major undertaking, but taking the right sequence of steps
and making some tough choices to reduce the scope of testing can make the chore
a little less daunting.
Why do applications break in Windows Vista and Windows 7?
So what changes were made in Windows 7 (and Windows Vista)
that caused applications designed for Windows XP to ‘break?’ To be sure, the engineering teams responsible
for Windows Vista and Windows 7 didn’t take the issue lightly.
The changes to Windows were made to improve security,
reliability, performance, and usability, and in some cases to remove legacy
components that have simply reached the end of their useful life. We won’t take the time to catalog all of the
changes in this article, but those most significant to application
compatibility include:
User Account Control (UAC)/Standard User accounts. In the development of Windows Vista, the
engineering team set out to enable most organizations to deploy their users as
standard users, and reserve administrator privileges for those who need them—IT
professionals. Adopting the principle of
what we used to call ‘least-privileged user account’ for client PCs helps
prevent intrusive malware, reduces end user configuration errors, and prevents
unauthorized applications from being loaded on the machine. In the past, an application had the ability
to write to the registry settings, modify the kernel, and other similarly
invasive actions. Unfortunately this
level of freedom came with a price—namely security. Windows now restricts the parameters of the
OS an application is able to change—limiting the impact any malware can
have—but applications that were written with this behavior will need to be
modified or shimmed to function in Windows 7.
Applications performing hard version checks for the Windows
XP operating system version are also affected. While it makes some sense for a
developer to lock support and functionality for the application with the version
of the operating system the developer originally used in testing, it also
assumes that users will never attempt to install that application on a newer
OS, or install a newer Service Pack to the same OS. While this is a relatively
easy issue to mitigate with compatibility modes or fixes, you will see this
surface frequently when coming from Windows XP to Windows 7.
The five steps to managing application readiness for Windows 7
Like most big undertakings, the challenge isn’t
insurmountable if you take the time to deconstruct the problem into logical,
manageable tasks.
An application readiness project falls into three major
sections: Collecting, Analyzing and Mitigating.
However, there are a couple of additional steps we would like to call
out: consider virtualization
technologies before you commence the testing regimen, to help reduce the
testing process and potentially help improve your desktop infrastructure to
make future migrations more manageable; and sequence the testing phase to align
to your roll-out strategy.
If you’re ready to dive in, let’s get started.
Step 1: Collect an application inventory
The first step is to take an application inventory to
understand exactly where you stand—and believe us; at this point you’ve
probably just realized the problem is bigger than you thought. But more importantly, you’ve just turned an
‘unknown’ into a ‘known’ and are in a better position to scope the testing and
readiness program and understand the challenges ahead.
Fortunately there are a number of tools available that can
help automate the process. Your client
management software might have this capability built-in, or you can also use
the Application
Compatibility Toolkit, available for free download. If you already have
another inventory mechanism like System Center Configuration Manager, Asset
Inventory Service or other, you can use that as a starting point.
To make the inventory most useful downstream, capture more
than just a list of applications—you’ll want to understand more detail on who
is using an application, what their role is, and how important that application
is to the user. With this information,
you can prioritize those mission-critical applications and eliminate unused or
redundant applications (more on that in the next step).
Also, there’s a side benefit—identifying widely-used
applications that you don’t currently manage.
You’ll want to get these into your orbit so you can ensure they are
properly managed, on the approved version and have the required software
updates.
Step 2: Analyze your
applications
How many applications do you currently support that have
been replaced or have otherwise fallen out of favor with business users? If you’re like most organizations, a sizable
number of them—in some cases most of them.
So once you done your assessment and have a good ‘lay of the land,’ the
next step is to scrub your supported application list and filter them down,
before you undertake the time consuming—and costly— process of regression
testing.
Set appropriate goals for your application portfolio. How many total apps do you want to
support? At what point does an app
elevate to “managed” status?
After you set your goals, it’s now time to find the low
hanging fruit and narrow down the applications that need testing.
- Eliminate redundant and unused
applications.You’ll undoubtedly find
that you have several applications that perform the same function. Now is a
good time to standardize on a single application per function, and eliminate
those that have been made obsolete. One tip here is to try and map application
dependencies, as you may need to support a legacy version of one application to
keep another one supported by the ISV.And of course drop those that are rarely or never used.Not only will you make testing easier, you
might save on licensing expense as well.
- Remove multiple versions of the same application
and standardize on the most current.In
almost all cases, the newest version performs best and is the most secure and
reliable. Again, watch for application-to-application dependencies.
Collect information from business users to help prioritize
those apps that are mission critical, and determine which departments are using
which apps. This will be useful when you
sequence your testing process; you’ll want to align the timing of your testing
to your staged roll-out of the new desktop image.
Step 3: Assess incompatibilities and mitigation
options
No doubt you will find some applications that need some work
to get them ready for Windows 7. At this
point you have several options:
- You can replace the non-compatible application
with a new version.Certainly the most
reliable method, but unfortunately, the most expensive as well.If the application is mission-critical or
otherwise strategic to operations, this is the way you’ll want to go.
- Create shims for your existing
applications.Shims are small pieces of
code inserted between the application and Windows to modify calls to the
underlying OS—for instance, to trick your application into thinking the user is
running as an administrator, while still maintaining standard user mode.You will have some management overhead, since
you’ll need to maintain a shim database, but this approach will remedy many
application problems.This is the more
cost effective route, and might be the only option if the application vendor is
no longer around.One caveat—many
vendors will not support shimmed applications.
- You can use Group Policy to change the offending
behavior of the application.Like
shimming, this will usually take care of the compatibility problem but carries
some downsides as well.Essentially this
approach uses policy to disable a particular feature or function that is
causing the application to falter.Unfortunately, in many cases these functions involve the security of the
underlying system, so the trade-off is significant.Likewise, the application must have Group
Policy settings to enable this manageability.
For custom or in-house developed applications, you can of
course modify the code. This isn’t
always an option, but if it is, there are great resources to help—the Application
Compatibility Cookbook for changes made from Windows XP to Windows Vista,
and the Application
Quality Cookbook for changes made from Windows Vista to Windows 7. Both are
free guides that help developers recode an application for native
compatibility.
Step 4: Prepare for
the OS deployment and new application delivery options
The start of an OS migration project is a great time to
rethink how you package and deliver applications to your end users. Virtualization technologies have opened up
options that simply weren’t available for the last major OS migration; you
should consider different models for desktop image and application delivery
before beginning the testing process. You
might find that the savings in application testing and readiness more than
offsets the cost of implementing a virtualized environment—while providing a
more flexible and easier-to-manage environment for future efforts.
There are two major forms of virtualization that can address
application compatibility issues—application virtualization and OS
virtualization. Application
virtualization separates the application layer from the OS, including the
applications files and registry settings, and packages the application for
streaming. OS virtualization come in a
few different forms, but essentially creates an OS image independent of the
native image on the machine.
Virtualizing your application portfolio provides a number of
benefits for manageability and flexibility, but one key advantage is that you
minimize application-to-application conflicts.
This type of conflict arises, for instance, when you need to run two
versions of the same application simultaneously—common in training situations
where you want to compare the process of conducting a specific task in an old
versus new application, or when the finance department is migrating to a newer
version of their accounting software but needs access to the old one to close
the fiscal year.
A more general use of virtualization to overcome application
compatibility is to create a virtual image that contains a critical application
and the operating system it is designed to run on. There are several tools to enable OS virtualization,
from Virtual PC and Windows XP Mode in Windows 7 Professional and higher SKUs
(an unmanaged virtual image that will run applications intended for Windows XP
but not compatible with Windows 7) to Microsoft Enterprise Desktop
Virtualization (MED-V), in the Microsoft Desktop Optimization Pack (MDOP),
which enables a virtual machine to be easily provisioned, configured and
managed using policies to determine how the physical and virtual environments
interact with one another.
Of course, adopting an alternative computing model for your
client PCs is an undertaking in its own right, but this would be the time to
assess whether the benefits to your organization—greater flexibility and
manageability—outweigh the additional effort to adopt this model for PC
provisioning.
Step 5: Sequence your
testing, piloting and deployment efforts
Use your prioritization from step 2 to sequence your testing
efforts, so you can begin the staged roll-out with and conduct subsequent
testing in parallel.
As you begin the testing process, you can use two approaches—static
and dynamic analysis; while static analysis is relatively new, a thorough
testing regimen will use both.
- Static analysis looks at the structure of the
application and identifies issues that will undoubtedly arise, either in
installation or runtime.There are a
number of tools and services that can help automate this process, and will
quickly highlight the obvious problems.
- Dynamic analysis looks at the behavior of the
application at runtime, and is what is traditionally done in regression testing.Here, you are “smoke testing” the application
in your specific environment—replicating the experience a variety of users will
have with their hardware and the other key applications and drivers.
- Finally, you will want to get a handful of real
users running the applications and looking for any strange behavior that hasn’t
surfaced in the structured testing.The
promise of keeping the new PC for participation can be a great motivator here!
Once you are ready to start rolling out into production, identify
the people for whom a migration makes sense first—based on specific
capabilities they need, or to minimize business disruption. Migrating a group of expert users will be
easier than dealing with the help desk calls from task workers who now are looking
at an unfamiliar screen and don’t know what to do with it. Next, identify which
applications these groups will need to perform their work. Start with groups
that are minimally or unaffected by application compatibility based on the
applications they use, this will enable you to validate the deployment process
and the operating system. As you work through your application portfolio and
more groups become unblocked from incompatible applications, then target those
groups.
One final word of caution—avoid taking the process too
far. If you let the scope creep from
application compatibility to a full-blown application quality project, you
might never finish. Accept the goal of
fixing bugs that prevent work from being done, and avoid trying to eliminate every
bug that exists—you undoubtedly have better use for your time!
More resources
Readying your application portfolio for a migration to
Windows 7 is a major undertaking, but fortunately there are a number of tools
and an abundance of guidance to make the process more streamlined and
manageable. We have just scratched the
surface in this article; if you’re ready to dive deeper and get the process
rolling, a great next step is to visit the Application
Compatibility zone on the Springboard
Series on TechNet, download the Application Compatibility Toolkit, and
start building your project plan!
You can also find helpful information and guidance on Chris Jackson’s Blog, and in the
Windows 7 Application Compatibility white paper, which covers Understanding
Application Compatibility and Understanding
Application Compatibility in Your Environment. You can learn more on the virtualization
technologies mentioned above at www.microsoft.com/mdop
and on the
MDOP TechNet page.
To learn more about Windows 7 or any of the Windows Client
technologies, please visit www.microsoft.com/springboard
for the latest in information, guidance, and community connections.