Planifier une analyse incrémentielle (Office SharePoint Server 2007)

Mise à jour : 2008-09-11

ImportantImportant :

You must be a shared services administrator to complete this procedure.

To schedule an incremental crawl

Use this procedure to create a new or change an existing incremental-crawl schedule for a particular content source.

Schedule an incremental crawl for a particular content source

  1. Complete one of the following steps depending on the status of your installation.

    • If the Mise à jour d’infrastructure pour les produits serveur de Microsoft Office is installed, in Central Administration, on the Quick Launch, in the Shared Services Administration group, click a shared service.

      On the Shared Services Administration page, in the Search section, click Search administration.

      On the Search Administration page, on the Quick Launch, in the Queries and Results section, click Content sources.

      NoteRemarque :

      For more information, see Description of the Microsoft Office Servers Infrastructure Update (https://go.microsoft.com/fwlink/?LinkID=121886).

    • If the Mise à jour d’infrastructure pour les produits serveur de Microsoft Office is not installed, in Central Administration, on the Quick Launch, in the Shared Services Administration group, click a shared service.

      On the Shared Services Administration page, in the Search section, click Search settings.

      On the Configure Search Settings page, in the Crawl Settings section, click Content sources and crawl schedules.

  2. On the Manage Content Sources page, right click the content source for which you want to schedule an incremental crawl and then click Edit.

  3. On the Edit Content Source page, in the Crawl Schedules section, do the following:

    • If an incremental crawl has never been created for this content source, click the Create schedule link below the Incremental Crawl list.

      -or-

    • If you are changing the incremental-crawl schedule, click the Edit schedule link below the Incremental Crawl list.

  4. In the Manage Schedules dialog box, in the Type section, select Daily, Weekly, or Monthly.

  5. In the Settings section, do the following:

    • In the Run every box, type the number of days between crawls. For example, to schedule an incremental crawl to start every other day, type 2.

    • In the Starting time list, select the time of the day from which to start the scheduled crawl.

    • If you want to crawl more frequently than once a day, select the Repeat within the day box and type the number of minutes to wait between crawls in the Every box and type the total number of minutes in which to repeat the crawl within the same day in the For box. For example, if you select Repeat within the day and type 60 in the Every box and 720 in the For box, an incremental crawl of the content source you are configuring starts every 60 minutes up to 720 minutes (12 hours) after the first scheduled incremental crawl for this content source ran.

  6. Click OK.