Enter a meter reading

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

You can set up meters to record substance flows from machines, extraction devices, and emission points. You can then enter the readings from a meter by using the Meter readings form.

  1. Click Compliance and internal controls > Common > Environmental sustainability > Meters.

  2. In the Meters form, select a meter, and then click Meter readings.

  3. Click New to enter a new meter reading.

  4. Enter the date and time that the meter was read, and enter the quantity that was recorded.

  5. If you did not read the meter, select the name of the employee who completed the reading. Then enter any other relevant information about the meter reading.