Hour forecasts (form)

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Click Project management and accounting > Inquiries > Forecasts > Hour.

–or–

Click Project management and accounting > Common > Projects > All projects. Select or open a project. On the Action Pane, on the Plan tab, in the Forecast group, click Hour forecasts.

–or–

Click Project management and accounting > Common > Projects > Project contracts. Select or open a project contract. On the Action Pane, on the Plan tab, in the Forecast group, click Hour forecast.

Use this form to enter the expected amount of hours on a project. During a project, you can track the progress of the project by comparing this forecasted number of hours with the actual number of hours spent on the project.

Tasks that use this form

Edit forecast transactions

Enter forecast transactions

The following tables provide descriptions for the controls in this form.

Tabs

Tab

Description

Overview tab

Enter new forecast transactions with the number of expected hours.

General tab

Enter additional identification information and view posting details.

Dates

View or enter date information.

Resource requirements

Define the resource requirements to be associated with an hour forecast.

Scheduling

View scheduling information and enter an activity.

Financial dimensions

View information about financial dimensions, such as the default dimensions and where the dimensions are used in account structures and advanced rule structures.

Buttons

Button

Description

Edit

Update, copy, or delete forecast transactions.

General ledger preview

View the general ledger entries for the selected transaction.

Transfer quotation lines

Register quotation lines of the type Hour as hour forecast lines.

Scheduling

Open a menu that contains the following items:

  • Scheduling – Schedule tasks for the project that the selected transaction is associated with.

  • Capacity load – View capacity reservations and view the available capacity on the operations resource for each date and day of the week.

  • Applicable resources – Select a resource to assign to an activity.

  • Gantt chart – Display a graphical overview of the current production plan that is scheduled for a project or manually reschedule the production.

Trade agreement

View records for a selected price discount group.

Fields

Field

Description

Forecast model

Select the forecast model defined for the project. You can also select a different forecast model.

Project date

Select the start date calculated for the current activity. By default, if you do not select a start date, the current date is entered.

Project ID

Select the project that you want to schedule for the forecast transaction.

Activity number

Select the activity for the forecast transaction.

Category

Select the appropriate category for the forecast transaction.

Worker

Select a worker ID to allocate a specific worker to a specific activity for the forecast transaction.

Description

Enter a description of the forecast transaction.

Hours

Enter the hours that you want to allow for the project.

Line property

Select the line property for the transaction.

Budget type

The type of budget information that this forecast holds.

  • Original – The forecast holds the project budget amount first committed.

  • Remaining – The forecast holds the project budget amount remaining. This amount is updated by transactions and by budget revisions.

  • Revision – The forecast holds the amounts by which a remaining budget was changed.

  • None – The forecast is not used for project budgeting control.

Cost price

Enter a cost price. The amount you enter here can override the default determined by the project pricing system.

Sales currency

Enter the invoice currency of the transaction for the forecast.

Exchange rate

Specify a fixed exchange rate for the sales price on the forecast.

Sales price

Sales price per hour of the current transaction.

Active

Indicates that the transaction is included in the forecast.

Modified by

Date when the record was last modified by user.

Line number

Displays line number for identification.

Resource

Specify the operations resource that should be used.

Link

Specifies the link that the job was created with. A link tells how the current job is tied to the subsequent job. The following options exist:

  • None or Blank – There is no link to the next job.

  • StartStart – The job must start at the same time the next job starts.

  • EndEnd – The job must end at the same time the next job ends.

  • EndStart – The job must end at the same time the next job starts.

  • StartEnd – The job must start at the same time the next job ends.

Note

Only when the link type is Hard are the times identical. When the link type is Soft, there may be a time gap between the two jobs. In other words, the next job can start later than the link specifies.

Examples

Examples of possible combinations of link type and link:

EndStart and Soft – used between operations.

EndStart and Hard – used between setup job and process job.

StartStart and Hard – used between several operations resources in the same operation.

Ended and Hard – used for secondary operations.

Link type

Indicates the attachment type. The field can have the following values:

  • Soft – This indicates that the job may be placed later than what the attachment defines.

  • Hard – This indicates that the following job must be placed as what the attachment defines.

Working time

Select this check box to schedule according to defined work time.

Capacity

If you select this check box, the planning function will reserve capacity on the current budget line if the planning is performed with limited capacity.

Invoice date

View the forecasted invoice date. The invoice date calculated for forecast transactions is based on the sum of the invoice date plus the invoice frequency defined on the invoice project.

Elimination date

View or modify the elimination date. When the forecast is created, the elimination date is set to the end date of the estimate project. If the estimate project has no end date, the project date will be applied. This applies to fixed-price projects and investment projects.

Cost payment date

Expected payment date of the cost. The date is calculated by adding project date and the terms of payment set up for expenses in the project parameters.

Sales payment date

Expected payment date of the revenue. The date is calculated by adding the invoice date plus individual buffer days from the contract project plus general buffer days from the project parameters.

Load

Specify the maximum capacity of the resource to assign to the selected transaction. Specify the capacity as a percentage.

Load displays the percentage of maximum capacity that has been reserved. The maximum capacity is specified in the work calendar.

Requirement type

The type of requirement that you want to specify for the activity.

You can specify multiple requirements for a forecast activity. For example, if you specify that a resource of type Human resources is needed, you can add Skill, Certificate, Course, or Title as requirements. Microsoft Dynamics AX will generate a list of resources that meet these criteria.

Select the requirement type from the following:

  • Resource type

  • Resource

  • Resource group

  • Capability

  • Skill (Requires the Human resources module.)

  • Courses (Requires the Human resources module.)

  • Certificate (Requires the Human resources module.)

  • Title (Requires the Human resources module.)

Requirement

The capability or classification that a particular resource of the selected type must possess.

Select the requirement from the drop-down list in the field. The contents are determined by the requirement type you selected in the Requirement type. For example, if you selected Resource type, the list displays all the resource types: Vendor, Human resources, Machine, Tool, and Location.

Operations scheduling

Select the check box to include the selected requirement in operations scheduling.

Job scheduling

Select the check box to include the selected requirement in job scheduling.

Working time

If you select this check box, the scheduled operation time will be determined by the working hours specified in the calendar attached to the current operations resource. If you leave the check box blank, Microsoft Dynamics AX cannot reserve capacity on the current budget line.

Resource

Displays the operations resource that is assigned to perform the job as soon as planning is finished.

Hours scheduled

Forecast lines can be divided into multiple lines. The operations resource available hours determines how a task is distributed over time considering how other tasks are already allocated.

Project date

The start date calculated for the current activity.

Start time

The start time calculated for the current activity.

End date

The end date calculated for the current activity.

End time

The end time calculated for the current activity.

Default financial dimensions

The default financial dimensions for the main account. When you select a financial dimension value, the Where the %1 dimension is used field group displays where the dimension is used in account structures and advanced rule structures.

Where the %1 dimension is used

The account structures and advanced rule structures that use the financial dimensions that you selected in the Financial dimensions or Default financial dimensions field group.

Note

The name of the field depends on the selection in the Financial dimensions or Default financial dimensions field group.

See also

Edit forecast transactions

Enter forecast transactions

Expense forecasts (form)

Fee forecasts (form)

On-account forecasts (form)

Item forecasts (form)

Route operations on route version (form)

Create and update routes (form)