Start production orders [AX 2012]

Updated: November 25, 2010

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Use this procedure to start production of the items in the selected production order.

  1. Click Production control > Periodic > Production orders > Start.

  2. Select the production order to start.

  3. On the Overview tab, in the Quantity field, enter the quantity to produce.

  4. In the Date field, enter the date that the production starts.

  5. In the fields From Oper. No. and To Oper. No., select the operation numbers to start and end the production.

  6. Select or clear the Start production check box.

  7. On the General tab, some of the fields are already filled based on the information that you entered in the Overview tab. However, you can change these values.

  8. Click OK.

Note Note

You can cancel a production order after it is started. Click Production control > Periodic > Production orders > Reset status.