About project costs [AX 2012]

Updated: March 22, 2011

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

This topic provides an overview of how to configure Microsoft Dynamics AX to post project costs for hours and expenses to profit and loss accounts. This configuration is set up in the Project groups form.

  • License code: Project I

  • Configuration code: Basic (none)

The following table shows how the account is applied.

Transaction type

Project type

Statement type

Hour

Time and material

Profit and loss

Expense

Fixed-price

Consumption

In the Project groups form, on the Ledger FastTab, select Profit and loss in the Journalizing lists.


Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).

Community Additions

ADD