Scheduling (class form)
Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012
Click Project management and accounting > Inquiries > Forecasts > Hour. Click the Scheduling button.
Use this form to schedule the tasks that are set up for the current project. Forecasts form the basis of any schedule. By using project scheduling, you can do the following:
Distribute activities over time.
Schedule resources on a project.
View capacity load for resources.
Modify a generated schedule.
Navigating the form
The following table provides descriptions for the controls in this form.
Fields
Field |
Description |
---|---|
Project ID |
Select the project to schedule activities to. |
Model |
Select the forecast model for the activity schedule. |
In/Out |
Select Forward or Backward to indicate whether the project should be scheduled forward or backward in time. |
Date |
Specify a date for the project start. |
Time |
Specify a time for the project start. |
Method |
Select a scheduling method. In most cases, the Operations scheduling option is sufficient for project scheduling. The level of detail in this scheduling method is fairly low compared to the level of detail in the Job scheduling method. By using this scheduling method, no specific operations resource is allocated. |
Sort using |
Select the sorting order for the project scheduling. |
Primary resource selection |
Determines the scheduling engine optimization strategy. The scheduling engine examines combinations of resources to identify those that satisfy requirements. You can specify selection criteria for the scheduling engine by selecting one of the following values in the Primary resource selection field:
|
Finite capacity |
View capacity limitations. The time reserved for activities that are already planned is deducted from the schedule. |
Keep production unit |
Select this check box to instruct the resource scheduling engine to use only resources that are bound to the production unit that is already selected. |
Schedule references |
Select this check box to include activities on all levels of the main project in the schedule. If you clear this check box, the only activities scheduled are those referring to the project that is specified in the Project field. |
Synchronize references |
Select this check box to specify which project determines the positioning of remaining projects, within one project hierarchy. That is, the project specified in the Project field determines the distribution of activities before, and after the specified project. |