Copy plan (class form)

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Click Master planning > Periodic > Plans > Copy plan.

Use this form to copy the current master scheduling results from one plan to another. Only the requirements and planned orders are copied, and not the plan itself or the configuration of the plan. You can view the results in the Requirement profile.

You can use the Copy plan function to copy the results of the static plan to the dynamic plan, for example. You can also set up a batch job to run daily.

The following tables provide descriptions for the controls in this form.

Enter criteria on the General tab

Submit a batch processing job from a form

Tabs

Tab

Description

General

Enter criteria on the General tab

Batch

Create a batch job

Buttons

Button

Description

Recurrence

Set up a permanent or temporary recurrence of the batch job.