Assign target completion dates to question groups in RapidStart Services [AX 2012]

Updated: September 17, 2015

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Beginning October 1, 2015, RapidStart services will no longer be supported. For more information, see the announcement on CustomerSourcehttps://mbs.microsoft.com/partnersource/northamerica/news-events/news/RapidStartServicesDiscontinued or PartnerSourcehttps://mbs.microsoft.com/customersource/northamerica/news-events/news-events/news/RapidStartServicesDiscontinued.

As the Customer administrator for a configuration project in Microsoft Dynamics ERP RapidStart Services, you can use this procedure to assign a target completion date to each group of questions in your configuration project. Target completion dates can help keep the work of answering questions on schedule.

  • The business experts know when they are expected to complete their work.

  • When you review progress reports for the project, you can see whether the business experts are on schedule to complete their work.

The target completion dates that you assign are based on Coordinated Universal Time (UTC), not a local system time.

NoteNote

For information about how to review the progress of a project, see Review the progress on questions in a configuration project in Microsoft Dynamics ERP RapidStart Services.

  1. In your browser, open online services at http://www.dynamicsonline.com.

  2. Click For Customers, and then click Sign in.

  3. Sign in by using the Microsoft account (formerly Windows Live ID) that is associated with your customer account in online services.

  4. If your logon credentials are associated with more than one organization in RapidStart Services, on the Choose your organization page, click the name of the organization to work with.

  5. On the Customer Portal dashboard, click Microsoft Dynamics® RapidStart.

  6. In the main area of the Getting started page, click Open an existing project.

  7. On the Projects page, click the row of the configuration project in which to assign a business expert to a group of questions.

    TipTip

    By default, the project list displays only the projects that you created. To see all configuration projects that have been created for your organization, in the Current view list, select All projects.

  8. In the Name column, click the name of the configuration project.

  9. At the top of the each question group box on the page, click the name of the person who is currently assigned to the question group.

  10. In the Reassign question group form, next to the Expected completion date field, click the calendar button, and then select a date.

    TipTip

    In the Reassign question group form, you can also reassign the question group to a different business expert.

  11. Click Reassign.

  12. If there is another page of question groups for your configuration project, click Next at the bottom of the page to continue assigning question groups.


Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).

Community Additions

ADD
Show: