How to Modify a Recovery Point Schedule

Applies To: System Center Data Protection Manager 2010

You can use the following procedure to modify the time and days of the week when DPM creates recovery points for a protection group.

To modify a recovery point schedule

  1. In DPM Administrator Console, click Protection on the navigation bar.

  2. In the display pane, select the protection group for which you want to modify the recovery point schedule.

  3. In the Actions pane, click Modify protection group. This starts the Modify Group Wizard.

  4. Select the group members for the protection group, and click OK.

  5. Select the data protection method, and click OK.

  6. On the Short-Term Goals screen, in the File Recovery Points pane, click Modify.

  7. Specify a new time, date, and days of the week for the recovery points, and click OK.

  8. Click Next, and then click Update Group.

See Also

Tasks

How to Create a Recovery Point

Concepts

What Is a Recovery Point?