Add a task to your task status (Project Server 2010)
Applies to: Project Server 2010
Topic Last Modified: 2011-04-13
While reporting task status in Microsoft Project Web App, you may find that you want to report on a task that is not showing up in the list.
-
On the Quick Launch, in the My Work section, click Tasks.
-
On the Tasks tab of the ribbon, in the Tasks group, click the arrow under Insert Row.
-
Choose how you want to add a task:
-
Create a New Task Create a new task within an existing project, and then add that task to your task status.
-
Add Yourself to a Task Assign yourself to an existing task, and then add that task to your task status.
-
Insert Team Tasks Assign yourself to one of your team tasks, and add that task to your task status.
-
Once you have added a task to your task status, you can enter your progress on that task.