Force check-in enterprise objects in Project Server
Summary: You can force the check-in of enterprise projects, resources, custom fields, calendars, lookup tables, and resource plans in Project Web App.
Applies to: Project Server Subscription Edition, Project Server 2019, Project Server 2016, Project Server 2013
If an enterprise object is checked out and the user who checked it out is unavailable or unable to check it back in, you can force a check-in.
Important
If you force check-in an enterprise object that a user is modifying, the modifications may be lost.
You can force check-in the following types of enterprise objects:
Enterprise projects
Enterprise resources
Enterprise custom fields
Enterprise calendars
Lookup tables for enterprise custom fields
Resource plans