Production flow activities upgrade (form)

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

Click Preprocessing upgrade checklist > Prepare application data for preprocessing. Click Prepare kanbans for migration or Prepare LOS schedules for migration. Click Next version base data > Production flows, and then click Activities.

Use this form to obtain an overview of the production flow activities that are created and configured for the selected production flow version. In the activities overview, multiple activities are listed in the order that they are created.

On the Predecessors and Successors tabs, you can view the upstream and downstream activities that are defined for the selected activity. These activities are configured with activity relations that define the activity sequence. You can update production flow versions that are not activated by adding or removing activities or activity relations.

The following tables provide descriptions for the controls in this form.

Tabs

Tab

Description

General

View information about the selected activity.

Predecessors

View the upstream activity or activities that are defined for the selected activity. The activity relations that are configured for these activities can carry sequence constraints. You can update a production flow version that is not activated by adding or removing an activity relation.

Successors

View the downstream activity or activities that are defined for the selected activity. The activity relations that are configured for these activities can carry sequence constraints. You can update a production flow version that is not activated by adding or removing an activity relation.

Buttons

Button

Description

Create new plan activity

Open the Create new plan activity wizard to create new activities for the production flow and add the created activity to the version.

Add predecessor

Open the Create activity relation form to add a new activity relation to the production flow version and to define the related end to start sequence constraint.

Add successor

Open the Create activity relation form to add a new activity relation to the production flow version and to define the related end to start sequence constraint.

Fields

Field

Description

Activity

View the identification of the activity.

Name

View the name of the activity.

Activity type

View the type of the activity.

Ratio

View the Cycle time ratio that is set up for the activity relation on the Create activity relation form.

See also

Production flows upgrade (form)

Production flow version details upgrade (form)

Create activity relation upgrade (form)

Create new plan activity upgrade (form)