Click Production control > Periodic > Manufacturing execution > Job registration.

Use this form to register time, material consumption, and costs for production jobs, projects, and indirect activities. Workers can be set up for different levels of registration. For example, some workers may only be able to make clock-in and clock-out registrations. Other workers may have to register every time that they start and complete a job, take a break, or participate in non-project activities.

NoteNote

The Job registration form can be configured for specific purposes and may contain different buttons and fields, depending on the setup.

The following table provides descriptions for the controls in this form.

NoteNote
The information is specific to Process manufacturing production and logistics.

For more information about the features and controls in this form, see:

 Job registration - resource (form).

Field

Description

CW start quantity

The quantity of catch weight items that you want to start producing on the production job.

CW requested quantity

The quantity of catch weight items that are planned for the operation.

CW started quantity

The quantity of catch weight items that are started on the production job.