Specify basic project schedule details

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2

Use this procedure to specify the basic parameters of a project schedule.

Note

The procedure for completing this task changed for cumulative update 7 or later for Microsoft Dynamics AX 2012 R2. The updated procedure also applies to AX 2012 R3. For more information, see the section later in this topic.

Specify basic project details

  1. Click Project management and accounting > Common > Projects > All projects. Select a project to create a schedule for.

  2. On the Action Pane, on the Project tab, in the Maintain group, click Edit.

  3. On the Scheduling and resource assignment FastTab, do the following:

    • In the Schedule start date and End date fields, specify the date range that you want the project to span.

    • In the Scheduling calendar field, select the scheduling calendar that you want to use to validate start dates and end dates for a project or activity.

    • In the Duration in days field, update the number of days that you want the project to last. If you make a change here, the end date that you entered for the project is changed.

    • In the Total effort in hours field, enter the number of total hours that are required to complete the project.

    • If you want to ignore the standard working hours that are specified in workers’ own calendars, select the Scheduling ignores the calendar of the resource check box.

      When you ignore the standard working hours for a worker, you increase your view of the worker’s capacity to 24 hours per day. This option is useful for planning purposes in special cases, such as for projects that have non-standard hour requirements, or when you know a worker will be visiting or reassigned to a different time zone to work on the project or activity.

Specify basic project details in cumulative update 7 for Microsoft Dynamics AX 2012 R2

  1. Click Project management and accounting > Common > Projects > All projects. Select a project to create a schedule for.

  2. On the Action Pane, on the Project tab, in the Maintain group, click Edit.

  3. On the Project team and scheduling FastTab, follow these steps:

    • In the Schedule start date and End date fields, specify the date range that you want the project to span.

    • If you want to ignore the standard working hours that are specified in workers’ own calendars, select the Disregard the workers' calendar check box.

      When you ignore the standard working hours for a worker, you increase your view of the worker’s capacity to 24 hours per day. This option is useful for planning purposes in special cases, such as for projects that have non-standard hour requirements, or when you know that a worker will be visiting or reassigned to a different time zone to work on the project or activity.

    • In the Scheduling calendar field, select the scheduling calendar to use to validate start dates and end dates for a project or activity.

    • In the Duration in days field, update the number of days that you want the project to last. If you make a change here, the end date that you entered for the project is changed.

    • In the Total planned effort in hours field, enter the number of total hours that are required to complete the project.

See also

Projects (form)

Assign resources (form)

Schedule resources (form)

Key tasks: Create a schedule based on a project in Microsoft Dynamics AX 2012 R2

Key tasks: Assign workers to projects based on availability

Key tasks: Create a schedule based on a project in Microsoft Dynamics AX 2012