Assign sequence values to an item

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2

Use this procedure to assign sequences and sequence values to an item, an item group, or all items.

  1. Click Master planning > Setup > Sequencing > Sequence value.

  2. Create a record.

  3. In the Sequence ID field, select the identification code of a sequence.

  4. In the Item code field, select one of the following options to indicate the item code and determine the value that you can select in the Item relation field:

    • Table – Assign the sequence to an item. If you select this option, you can then select the identification code of the item in the Item relation field.

    • Group – Assign the sequence to an item group. If you select this option, you can then select the identification code of the item group in the Item relation field.

    • All – Assign the sequence to all the items. If you select this option, the Item relation field is not available.

  5. In the Item relation field, select the item or item group to assign the sequence and the sequence value to.

    Note

    This field is available only if you select either Table or Group in the Item code field.

  6. In the Value field, select the sequence value to assign to the item, the item group, or all items.

See also

Set up product sequences

Set up sequence groups