Key Deployment Assumptions

Software License Costs

 

Users receiving upgrade

6,549

Software license cost (per computer)

$0   

Training Costs

 

Training hours per upgraded  user

1 hour

Training cost (cost to develop training per user)

$6

Desktop Deployment Costs

 

Desktop Imaging

 

Number of images currently used

13

Number of different hardware setups that require separate images

2

Number of different departmental setups that require separate images

6

Estimated IT time required to create each image

93 hours

Images required with the Windows Vista operating system

13

Application Compatibility Remediation

 

Number of core applications requiring testing for Windows Vista deployment

112

Average hours of testing per application

9 hours

Percentage of applications that will require remediation

15%

Average time spent per application requiring remediation

12 hours

Third-party application costs per user

-   

Infrastructure Remediation

 

Standard hardware refresh cycle

36 months

Additional desktops replaced for Windows Vista deployment

1,119

Desktops requiring upgrades

100

Additional laptops replaced for Windows Vista deployment

197

Laptops will requiring hardware upgrades

50

Expected Hardware Costs

 

   New desktop

$900

   New laptop

$1,600

   Upgrade desktop (hardware + labor)

$150

   Upgrade laptop (hardware + labor)

$150

Planning & Organization

 

Planning and organization time required

1,000 hours

Deployment Process

 

End-user downtime

0.12 hour

Deployment Method Used (depends on connection bandwidth and management infrastructure)

 

Manual Deployment

5%

Lite Touch Deployment

15%

Zero Touch Deployment

80%

The following financial calculations are estimates based on information available through calculation tools and industry research. The final budgeting and basis for which items shall be included in this project require an in-depth audit and confirmation. Of note are the exclusions of hardware purchases intended to be refreshed during the coming year as well as hardware that is more than three years old and overdue for refresh. The costs of the Enterprise Agreement for Microsoft desktop operating systems and Office products are also excluded from this calculation. The Enterprise Agreement in place includes the software licenses associated with this project.

Key Financial Indicators

 

Year One

Year Two

Year Three

Total

Cost

($1,983,000)

 

 

($1,983,000)

Operating System Benefits

$1,643,490

$1,643,490

$1,643,490

$4,930,470

Net Cash Flow

($339,510)

$1,643,490

$1,643,490

$2,947,470

Net Present Value (NPV)

($339,510)

$1,429,122

$1,242,715

$2,332,327

Discount Rate

 

 

 

15%

IRR

 

 

 

64%

Payback Period ( (Total Investment/Total Benefits) × 12)

 

 

 

14 months

Number of Desktops Deployed

 

 

 

6549

Cost per Desktop

 

 

 

($303)

   Software

 

 

 

($0)

   Training

 

 

 

($43)

   Planning & Imaging

 

 

 

($5)

   Application Remediation

 

 

 

($9)

   Hardware

 

 

 

($205)

   Planning

 

 

 

($7)

   Deployment Process

 

 

 

($34)

Cost Breakdown

Cost Type

One-Time Amount

Software

($0)

Training

($279,000)

Imaging

($31,000)

Application Remediation

($58,000)

Hardware

($1,345,000)

Planning

($48,000)

Deployment Process

($222,000)

Total Costs

($1,983,000)

Benefits Analysis

The following table displays the main benefits from Windows Vista and Office Enterprise 2007. Operating system and additional benefits have been calculated for three years; benefit calculation assumes the years begin after all deployments are complete.

Quantified Annual Operating System Benefits

Business Benefits

IT Department Benefits

Annual Benefits

Reduced Security Mgmt

$222,000

Reduced Information Theft

$90,000

PC Recycling

$26,000

Automated Desktop Management

$100,000

Reduced Help Desk Support

$104,000

Reduced Image Management

$25,000

Third-Party Application Savings

$65,490

Performance and Reliability

$518,000

Computer Failures

$3,000

Power Management

$195,000

Application Responsiveness

$6,000

Information Management

$289,000

Total Benefits

$1,643,490

Total annual benefits resulting from this project are $1,643,490. These benefits were derived using the Windows Vista early adopter data from Microsoft and take into account the assumptions stated in the “Project Description” section.

Download

Get the Microsoft Solution Accelerator for Business Desktop Deployment 2007

Update Notifications

Sign up to learn about updates and new releases

Feedback

Send us your comments or suggestions