Check-in enterprise calendars in Project Server
Summary: You can force check-in of an enterprise calendar by using Project Web App Settings.
Applies to: Project Server Subscription Edition, Project Server 2019, Project Server 2016, Project Server 2013
You can force the check-in of an enterprise calendar that is checked out. Note that forcing a check-in of an enterprise calendar that is being modified by a user may result in the loss of those changes.
Use the following procedure to force check-in enterprise calendars.
To force check-in enterprise calendars
On the Server Settings page, click Force Check-in Enterprise Objects.
From the Select the type of object you want to force check-in drop-down list, select Enterprise Calendars.
Select the calendars that you want to check in.
Click Check In.