Copy BOM (form)
Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012
Click Inventory management > Common > Bills of materials. Click Lines. Click Functions, and then click Copy.
Use this form to select a bill of materials (BOM) or route in either base data or production and make a copy of it. You can define where you want to place the copy and whether you want the copy to be added to the new location or to replace existing lines in the new location.
Note
Please note the following conditions when you use multiple sites:
When you copy an existing BOM to a different site, the warehouse on the BOM lines is cleared. However, if the site that you copy from and the site that you copy to are the same, the warehouse is not cleared.
When you copy an existing route to a different site, the operations resource on the route lines is cleared, and the default operations resources for the route relations are also cleared.
Navigating the form
The following table provides descriptions for the controls in this form.
Fields
Field |
Description |
---|---|
Copy from |
Section of the form where you define the Copy from settings. |
Base data |
Select Base data and enter information in the relevant fields to copy the BOM or route from base data. |
BOM number |
Enter the BOM number to copy from. |
Site |
If you are using multisite, enter the site associated with the BOM. |
Item number |
Select the item number that the BOM or route is attached to. |
Configuration |
Select a BOM configuration if the BOM that you want to copy is configurable. If the BOM is not configurable, the field is not active. |
Production |
Click to include a production order number for this item. |
Production number |
This field becomes available if you select |
BOM date |
Enter the date to use when the program searches for BOM lines to copy from. Only lines that are valid on the date that you enter are copied from. If this field is blank, all lines are copied. |
BOM number |
Select or specify the BOM number. |
Production |
Select this option to include a production order with the new BOM. |
Production number |
Select the production order that the BOM or route is to be copied from. |
Copy to |
Section of the form where you specify the Copy to settings. |
Base data |
Select this option to copy the BOM or route to base data. |
BOM number |
Select or specify the BOM number. |
Site |
If you are using multisite, enter the Site to be associated with the new BOM. |
Production |
Select this option if you want to copy the BOM or route to production. |
Production number |
Specify which production BOM you want to copy the BOM or route to. |
Update BOM number |
Select the check box to update the BOM number on the production. |
Setup |
Field group heading. |
Replace |
Select this option to replace lines on the BOM or route to which you are copying. |
Add |
Select this option to add lines on the BOM or route to which you are copying. |
Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).