(PM) Change feedback (form)

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

The path to this form varies depending on how access to the form is configured.

Click Production control > Periodic > Manufacturing execution > Change feedback. In the Select resource and action form, select and open a resource.

–or–

Click Production control > Periodic > Manufacturing execution > Job registration. In the Select resource and action form, select and open a resource. In the Job registration form, log on. In the Select resource and action form, select a resource, and then click Job history.

Use this form to modify feedback that has been entered on production jobs.

The following table provides descriptions for the controls in this form.

Note

The information is specific to Process manufacturing production and logistics.

For more information about the features and controls in this form, see:

 Change feedback (form).

Fields

Field

Description

CW qty requested

The quantity of catch weight items that are planned for the operation.

CW good qty

The catch weight quantity of produced items that meets quality standards.

CW error qty

The catch weight quantity of produced items that is defective.

Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).