Delivering a report to the SQL Server Report Server Cache

適用於: Operations Manager 2007 R2, Operations Manager 2007 SP1

You can create a schedule for sending reports to the cache in the SQL Server 2005 Report Server. When you do this, you shorten the time required to retrieve a report, which can be helpful if a report is large or is accessed frequently. For more information about report caching, see https://go.microsoft.com/fwlink/?LinkId=77536.

To schedule the delivery of a report to the SQL Report Server Cache

  1. In the Operations console, click Reporting.

  2. In the Reporting pane, click Favorite Reports.

  3. In the Favorite Reports pane, right-click the availability report you saved as a favorite, and then click Schedule.

  4. In the Subscribe to a Report Wizard, on the Delivery Settings page, do the following:

    1. Type a description in the Description text box.

    2. In the Delivery method list, click Null Delivery Provider.

    3. Click Next.

  5. On the Subscription Schedule page, do the following:

    1. Select one of the Generate the report options.

    2. In the The Subscription is effective beginning list, type a start date and a start time for the reports that you want to generate. You can also enter the date when this subscription will end in The subscription will end list, and then click Next.

  6. On the Parameters page, specify a span of time for the report in the From and To lists, make any other changes you need for this report, and then click Finish.